Installing the Components in the Type-A Multi-Purpose
Fiber Management Cabinet
Installation on the concrete floor: Place the insulation pads and type-A multi-purpose fiber management
cabinets at the planned positions, and align the installation holes of the insulation pads with the
corresponding expansion bolt holes, as shown in the following figure.
Installation on the ESD floor: Lift the type-A multi-purpose fiber management cabinet onto the support,
and align the installation holes of the type-A multi-purpose fiber management cabinet with the bolt holes
of the support.
Cross-sectional view of the
fiber management cabinet
bottom
Combine cabinets. The bottom connecting plate is placed at the bottom right position of the left-side type-A
fiber management cabinet. Before combining the cabinets, take the bottom connecting plate from the
packing position, as shown in the following figure.
Cabinet combination
at the lintel
Cabinet combination
at the bottom
39
M5
3.1±0.31 N· m