Verify that utility voltage and frequency
are correct in the transfer switch. In 3-
phase applications, you will also need to
verify phase rotation.
If phase rotation is incorrect, switch the
A and C connections in the generator
connection box and check phase rotation
again. Refer to the Installation Manual for
correct procedures.
With utility power present and the
generator OFF, select MANUAL in the
transfer switch and open the main
breaker.
Select MANUAL on the generator control
panel to start the generator with no loads
present.
If the Low Gas Pressure alarm goes off
or the Low Fuel Pressure indicator shows
on the control panel display, contact the
plumber who installed the gas lines.
To check automatic operation, shut off the
generator; then turn the key to AUTO and
close the main breaker.