To schedule a UPS On/Off task:
1 Click Add UPS On/Off to open the UPS On/Off window (see Figure 81).
Figure 81. UPS On/Off Window
2 Select how often to perform the UPS On/Off task: Once or Weekly.
3 Select the start dates and times for the UPS On/Off tasks.
NOTE:
The scheduled date and time cannot conflict with another scheduled UPS task.
The UPS Power Off time range (from shutdown to next startup) is 1 to 9999 minutes (the maximum
time is 6 days, 22 hours, and 39 minutes). The range for the year is 2009–2035.
4 Select the UPS to turn off and on.
Configuring the Software