User Manual
Cabling Requirements
Issue 05 (2024-01-19)
Before performing operations on the equipment, check that all tools meet the
requirements and record the tools. After the operations are complete, collect
all of the tools to prevent them from being left inside the equipment.
Before installing power cables, check that cable labels are correct and cable
terminals are insulated.
When installing the equipment, use a torque tool of a proper measurement
range to tighten the screws. When using a wrench to tighten the screws,
ensure that the wrench does not tilt and the torque error does not exceed
10% of the specified value.
Ensure that bolts are tightened with a torque tool and marked in red and blue
after double-check. Installation personnel mark tightened bolts in blue.
Quality inspection personnel confirm that the bolts are tightened and then
mark them in red. (The marks must cross the edges of the bolts.)
After the installation is complete, ensure that protective cases, insulation
tubes, and other necessary items for all electrical components are in position
to avoid electric shocks.
If the equipment has multiple inputs, disconnect all the inputs before
operating the equipment.
Before maintaining a downstream electrical or power distribution device, turn
off the output switch on the power supply equipment.
During equipment maintenance, attach "Do not switch on" labels near the
upstream and downstream switches or circuit breakers as well as warning
signs to prevent accidental connection. The equipment can be powered on
only after troubleshooting is complete.
Do not open equipment panels.
Check equipment connections periodically, ensuring that all screws are
securely tightened.
Only qualified professionals can replace a damaged cable.
Do not scrawl, damage, or block any labels or nameplates on the equipment.
Promptly replace labels that have worn out.
Do not use solvents such as water, alcohol, or oil to clean electrical
components inside or outside of the equipment.
When selecting, installing, and routing cables, follow local safety regulations
and rules.
When routing power cables, ensure that there is no coiling or twisting. Do not
join or weld power cables. If necessary, use a longer cable.
Ensure that all cables are properly connected and insulated, and meet
specifications.
Ensure that the slots and holes for routing cables are free from sharp edges,
and that the positions where cables are routed through pipes or cable holes
are equipped with cushion materials to prevent the cables from being
damaged by sharp edges or burrs.
Copyright © Huawei Digital Power Technologies Co., Ltd.
1 Safety Information
4

Advertisement

Table of Contents
loading

This manual is also suitable for:

Emma-a01Emma-a02

Table of Contents