Verifying The Installation And Cable Connections - Huawei STS-3000K-H1 Installation Manual

Smart transformer station
Table of Contents

Advertisement

STS-(3000K, 6000K)-H1 Smart Transformer Station
(Spain, Eiffage Turroneros)
Installation Guide
8
No.
1
2
3
4
5
6
7
8
Issue 02 (2020-02-21)
Verifying the Installation and Cable
Acceptance criteria
All onsite components are installed correctly and securely.
All switches are OFF.
All cables are connected correctly and securely.
All screws are tightened.
Unused cable holes are covered with waterproof caps.
The cable holes in use are sealed.
The installation space is proper, and the installation environment is clean
and tidy.
All doors of the STS are closed and properly locked.
Copyright © Huawei Technologies Co., Ltd.

8 Verifying the Installation and Cable Connections

Connections
67