ESS-240V12-(9AhBPVBA04, 7AhBPVBA04) Battery
Pack
Quick Guide
Wear protective gloves when removing and installing the support base
components to prevent injury.
Step 3 Install two support bases for each group of battery packs as follows: Place support
bases on the floor, ensure that the distance between the two support bases is at
least 280 mm, and then place battery packs on the support bases in sequence.
Step 4 After the installation is complete, seal the four screw holes on the top with rubber
plugs that are delivered with the battery packs.
Figure 4-13 Installing battery packs
----End

4.4 Cable Connection

4.4.1 Connecting Cables to Battery Packs for the UPS2000-G-6
kVA/10 kVA
Connecting Cables to Battery Packs for a Single UPS2000-G-6 kVA/10 kVA
Issue 02 (2022-06-30)
CA UTION
NO TE
If more than one battery pack is connected to the 6 kVA/10 kVA UPS, connect the battery
packs in parallel and then connect them to the UPS battery input ports.
NO TE
The following wiring diagram uses a standard UPS with one battery pack as an example.
Copyright © Huawei Digital Power Technologies Co., Ltd.
4 Installation
36

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Ess-240v12-7ahbpvba04

Table of Contents