ABB PVI-8.0-TL-OUTD Product Manual

ABB PVI-8.0-TL-OUTD Product Manual

Solar inverters
Hide thumbs Also See for PVI-8.0-TL-OUTD:
Table of Contents

Advertisement

Quick Links

ABB solar inverters
Product manual
PVI-6.0/8.0/10.0/12.5-TL-OUTD
(6.0 to 12.5 kW)

Advertisement

Table of Contents
loading

Summary of Contents for ABB PVI-8.0-TL-OUTD

  • Page 1 ABB solar inverters Product manual PVI-6.0/8.0/10.0/12.5-TL-OUTD (6.0 to 12.5 kW)
  • Page 2 Operators are required to read this manual and scrupulously follow the indications reported in it, since ABB cannot be held responsible for damages caused to people and/or things, or the equipment, if the warranty conditions are not observed.
  • Page 3 2 - Characteristics 3 - Safety and accident prevention 4 - Lifting and transport 5 - Installation 6 - Instruments 7 - Operation 8 - Maintenance PVI-6.0/8.0/10.0/12.5-TL-OUTD-Product manual EN-Rev B(M000023BG) EFFECTIVE 12/01/2015 © Copyright 2015 ABB. All Rights Reserved. - 3 -...
  • Page 4: Ntroduction And General Information

    ABB accepts no liability for failure to comply with the instructions for correct installation and will not be held responsible for systems upstream or downstream the equipment it has supplied.
  • Page 5: Table Of Contents

    1- Introduction and general information ontents ntroduction and general information ....................4 Warranty and Supply Conditions ......................4 Not included in the supply .......................4 Contents ..............................5 Reference number index ........................8 Graphical representation of references ....................8 The document and who it is for ......................9 Purpose and structure of the document .................9 List of annexes ........................9 Staff characteristics .........................9...
  • Page 6 1- Introduction and general information Residual risks ............................35 Table of residual risks ......................35 ifting and transport ........................36 General conditions ..........................36 Transport and handling .......................36 Lifting .............................36 Unpacking and checking ......................36 List of components supplied ....................37 Weight of the groups of device .....................38 nstallation ............................
  • Page 7 1- Introduction and general information LED behaviour ............................68 Specifications on the operation of the LEDs.................69 LED insulation fault .......................69 Description of the menus ........................70 General information ......................70 Statistics Menu ........................72 Settings Menu ........................74 Info Menu ..........................82 AUTOTEST procedure in accordance with standard CEI 0-21 ............83 Running the tests from the display menu ................83 aintenance .............................
  • Page 8: Reference Number Index

    1- Introduction and general information eference number index , Bracket , DC Disconnect switch , AC Output terminal block , Heat sink , Input connectors (MPPT1) , Channel configuration switch , Front cover , Input connectors (MPPT2) , Internal battery , LED Panel , AC cable gland , Signal terminal block...
  • Page 9: The Document And Who It Is For

    1- Introduction and general information he document and who it is for urpose and structure of the document This operating and maintenance manual is a useful guide that will enable you to work safely and carry out the operations necessary for keeping the equipment in good working order.
  • Page 10: Symbols Ad Signs

    1- Introduction and general information ymbols ad signs In the manual and/or in some cases on the equipment, the danger or hazard zones are indicated with signs, labels, symbols or icons. Table: Symbols This points out that it is mandatory to consult the manual or original do- cument, which must be available for future use and must not be dama- ged in any way.
  • Page 11: Field Of Use, General Conditions

    1- Introduction and general information ield of use, general conditions ABB shall not be liable for any damages whatsoever that may result from incorrect or careless operations. You may not use the equipment for a use that does not conform to that provided for in the field of use.
  • Page 12: Haracteristics

    Characteristics eneral conditions A description of the characteristics of the equipment is given so as to identify its main components and specify the technical terminology used in the manual. Technical terminology and the fast retrieval system for information, are supported by: •...
  • Page 13: Models And Range Of Equipment

    2 - Characteristics odels and range of equipment The specific models of three-phase inverters covered by this manual are divided into four groups according to their maximum output power: 6.0 kW, 8.0kW, 10.0 kW or 12.5 kW. For inverters of equal output power the variant between the various mo- dels is the presence or lack thereof of the DC disconnect switch , or the input fuses board...
  • Page 14: Identification Of The Equipment And The Manufacturer

    2 - Characteristics dentification of the equipment and the manufacturer The technical data shown in this manual do not in any case replace those shown on the labels attached to the equipment. The labels attached to the equipment must NOT be removed, damaged, dirtied, hidden, etc. The approval label contains the following information: 1.
  • Page 15 The officially required information is located on the approval label. The identification label is an accessory label which shows the information necessary for the identification and cha- racterisation of the inverter by ABB. N.B. The labels must NOT be hidden with objects and extraneous parts (rags, boxes, equip- ment, etc.);...
  • Page 16: Characteristics And Technical Data

    2 - Characteristics haracteristics and technical data Table: Technical Data PVI-6.0-TL-OUTD PVI-8.0-TL-OUTD PVI-10.0-TL-OUTD PVI-12.5-TL-OUTD Input Absolute Maximum 900 V Input Voltage (V max,abs Rated Input Voltage (V 580 V Input start-up voltage (V 360 V (adj. 250...500 V) start Input operating interval 0.7 x Vstart...850 V...
  • Page 17 2 - Characteristics Table: Technical Data PVI-6.0-TL-OUTD PVI-8.0-TL-OUTD PVI-10.0-TL-OUTD PVI-12.5-TL-OUTD Output AC Connection to the grid Three phase 3W or 4W+PE Nominal AC output voltage (V 400 V Output voltage range 320...480 V ...V acmin acmin Nominal AC Output Power...
  • Page 18 2 - Characteristics Table: Technical Data PVI-6.0-TL-OUTD PVI-8.0-TL-OUTD PVI-10.0-TL-OUTD PVI-12.5-TL-OUTD Physical Environmental Protection Rating IP 65 Cooling System Natural Overvoltage rating as per II (DC input) III (AC output) IEC 62109-1 Dimensions (H x W x D) 716mm x 645mm x 224mm / 28.2” x 25.4” x 8.8”...
  • Page 19: Tightening Torques

    2 - Characteristics ightening torques To maintain the IP65 protection of the system and for optimal installa- tion, the following tightening torques must be used: AC cable gland M40 (ring nut fixing) 5.0 Nm AC cable gland M40 (locknut fixing) 8.0 Nm Service cable glands M20 (ring nut fixing)
  • Page 20: Bracket Dimensions

    2 - Characteristics racket dimensions The wall mounting bracket dimensions are expressed in mm and inches 90.5 mm 3.56 in 50.0 mm 1.96 in 8.0 mm 0.31 in 25.0 mm 0.98 in 7.0 mm 0.28 in - 20 -...
  • Page 21: Efficiency Curves

    PVI-6.0-TL-OUTD - Efficiency curves PVI-6.0-TL-OUTD-S PVI-6.0-TL-OUTD-FS 100% 270 Vdc 580 Vdc 740 Vdc 100% % of Rated Output Power PVI-8.0-TL-OUTD PVI-8.0-TL-OUTD - Efficiency curves PVI-8.0-TL-OUTD-S PVI-8.0-TL-OUTD-FS 100% 270 Vdc 580 Vdc 740 Vdc 100% % of Rated Output Power - 21 -...
  • Page 22 2 - Characteristics PVI-10.0-TL-OUTD PVI-10.0-TL-OUTD - Efficiency curves PVI-10.0-TL-OUTD-S PVI-10.0-TL-OUTD-FS 300 Vdc 580 Vdc 750 Vdc 94% 100% % of Rated Output Power PVI-12.5-TL-OUTD PVI-12.5-TL-OUTD - Efficiency curves PVI-12.5-TL-OUTD-S PVI-12.5-TL-OUTD-FS 360 Vdc 580 Vdc 750 Vdc 100% % of Rated Output Power - 22 -...
  • Page 23: Power Derating

    2 - Characteristics ower derating In order to allow inverter operation in safe thermal and electrical condi- tions, the unit automatically reduces the value of the power fed into the grid. Power limiting may occur due to: • Adverse environmental conditions (thermal derating) •...
  • Page 24: Power Reduction Due To The Input Voltage

    The graphs show the automatic reduction of supplied power when input voltage values are too high or too low. PVI-6.0-TL-OUTD Pout Vs Vin (single input channel) PVI-6.0-TL-OUTD-S PVI-6.0-TL-OUTD-FS PVI-8.0-TL-OUTD 9000 PVI-8.0-TL-OUTD-S 8000 PVI-8.0-TL-OUTD-FS 7000 PVI-10.0-TL-OUTD PVI-10.0-TL-OUTD-S...
  • Page 25: Characteristics Of A Photovoltaic Generator

    2 - Characteristics haracteristics of a photovoltaic generator A PV generator consists of an assembly of photovoltaic panels that tran- sform solar radiation into DC electrical energy and can be made up of: Strings: X number of PV panels connected in series Array: group of X strings connected in parallel trings and Arrays In order to considerably reduce the cost of installing a photovoltaic sy-...
  • Page 26: Description Of The Equipment

    2 - Characteristics escription of the equipment This equipment is an inverter that converts direct electric current from a photovoltaic generator into alternating electric current and feeds it into the national grid. Photovoltaic panels transform energy from the sun into direct current (DC) electrical energy (through a photovoltaic field, also called photovol- taic (PV) generator;...
  • Page 27: Connection Of Several Inverters Together

    A configuration program that can help to correctly size the photovoltaic system is available on the web site of ABB - 27 -...
  • Page 28: Functionality And Components Of The Equipment

    The inverter or a network of several inverters, can also be monitored re- motely via an advanced communication system based on a RS-485 se- rial interface. The range of optional ABB devices that can be connected to this communication line allow you to monitor the device locally or re- motely through an internet connection.
  • Page 29: Topographic Diagram Of The Equipment

    2 - Characteristics opographic diagram of the equipment The diagram summarises the internal structure of the inverter. The main blocks are the DC-DC input converters (called "boosters") and the output inverter. The DC-DC converter and the output inverter both work at a high switching frequency, and so are small and relatively light. Each of the input converters is dedicated to a separate array, with inde- pendent maximum power point tracking (MPPT) control.
  • Page 30 2 - Characteristics - 30 -...
  • Page 31: Safety Devices

    2 - Characteristics afety devices nti-Islanding In the event of a local grid outage by the electricity company, or when the equipment is switched off for maintenance operations, the inverter must be physically disconnected to ensure the protection of the people working on the grid, in accordance with the relevant national laws and regulations.
  • Page 32: Afety And Accident Prevention

    ABB accepts no liability for failure to comply with the instructions for correct installation are cannot be held responsible for the systems upstream or downstream of the equipment it has supplied.
  • Page 33: Hazardous Areas And Operations

    These conditions are reported on the thecnical data and on installation chapter. ABB CANNOT be held responsible for disposal of the equipment: displays, cables, batteries, accumulators, etc., and therefore the customer must...
  • Page 34: Thermal Hazard

    ABB has eliminated sharp edges and corners, but in some cases it is not possible to do anything, and we therefore advise wearing the clothing and personal protective devices provided by the employer.
  • Page 35: Residual Risks

    3 - Safety and accident prevention esidual risks Despite the warnings and safety systems, there are still some residual risks that cannot be eliminated. These risks are listed in the following table with some suggestions to prevent them. able of residual risks RISK ANALYSIS AND DESCRIPTION SUGGESTED REMEDY Noise pollution due to installation in unsuitable environments or where...
  • Page 36: Ifting And Transport

    ABB usually stores and protects individual components by suitable means to make their transport and subsequent handling easier, but as a rule it is necessary to turn to the experience of specialized staff in change of loading and unloading the components.
  • Page 37: List Of Components Supplied

    4 - Lifting and transport ist of components supplied Supplied with the inverter are all the components required to correctly install and connect the inverter Components available for all models Bracket for wall fastening Plugs and screws for wall mounting 5 + 5 D.18 washer M40 Cable Gland...
  • Page 38: Weight Of The Groups Of Device

    4 - Lifting and transport eight of the groups of device Table: Weights Weight (Kg/lb) Lifting points (no.#) INVERTER <41.0 kg / 90.4 lb - 38 -...
  • Page 39: Nstallation

    Installation eneral conditions Installation of the equipment is carried out based on the system and the place in which the equipment is installed; therefore, its performance depends on the correctness of the connections. Staff authorised to carry out the installation must be specialised and experienced in this job;...
  • Page 40: Environmental Checks

    5 - Installation nvironmental checks • Consult the technical data to check the environmental parameters to be observed (degree of protection, temperature, humidity, altitude, etc.) • The installation to direct sunlight must be avoid beacuse it may cause: - phenonmena of power limitation by the inverter (with consequent reduc- tion of energy production) - premature aging of electronic/electromechanical components - premature aging of mechanical components (gaskets) and user inter-...
  • Page 41: Installation Position

    5 - Installation nstallation position When choosing the place of installation, comply with the following condi- tions: • Install on a wall or strong structure suitable for bearing the weight. • Install in safe, easy to reach places. • If possible, install at eye-level so that the display and status LEDs can be seen easily.
  • Page 42: Wall Mounting

    5 - Installation all mounting During installation do not place the inverter with the front cover facing towards the ground. • Position the bracket so that it is perfectly level on the wall and use it as a boring template. •...
  • Page 43: Operations Preparatory To Pv Generator Connection

    All ABB string inverters marketed in Europe are equipped with a device for protection against ground faults in accordance with the safety stand- ard set in Germany by Standard VDE V 0126-1-1:2006-02 (please refer to section 4.7 of the Standard).
  • Page 44 B ground fault interrupter. In accordance with article 712.413.1.1.1.2 of Section 712 of IEC Standard 64-8/7, we hereby declare that, because of their construction, ABB inverters do not inject ground fault direct currents. The use of an AC type circuit breaker with differential thermal magnetic protection with trip- ping current of 300 mA is advisable so as to prevent false tripping, due to the normal capaci- tive leakage current of photovoltaic modules.
  • Page 45: Independent Or Parallel Input Channels Configuration

    5 - Installation ndependent or parallel input channels configuration All the inverter models are equipped with two input channels (thus bene- fiting from two trackers for MPPT maximum power point tracking) which work independently of one another, which can be paralleled by levera- ging a single MPPT.
  • Page 46: Channel Configuration Examples

    5 - Installation Channel configuration examples PV generator characteristics MPPT configu- Notes ration A NECESSARY condition so that the two The photovoltaic generator consists of strings having a different number MPPTs can be used in independent mode is for MPPT configu- of modules in series from each other.
  • Page 47: Independent Channel Configuration (Default Configuration)

    5 - Installation ndependent channel configuration (default configuration) This configuration involves the use of the two input channels (MPPT) in independent mode. This means that the jumpers between the two channels (positive and negative) of the DC input terminal block must not be installed and the switch located on the main board must be set to “IND”.
  • Page 48: Input Connection To Pv Generator (Dc Side)

    5 - Installation nput connection to PV generator (DC side) Once preliminary checks have been carried out and no problems found with the photovoltaic system, and the channel configuration has been se- lected (parallel or independent) you may connect the inputs to the inverter. When the photovoltaic panels are exposed to sunlight they provide continuous DC voltage to the inverter.
  • Page 49 5 - Installation According to the system configuration, check the correct setting of the channels to indepen- dent or in parallel mode. An incorrect setting of the input channels can lead to loss of energy production. Polarity inversion can cause serious damage. Check polarity before connecting each string! Connect all the strings required by the system, always checking the seal of the connectors.
  • Page 50: String Protection Fuses (-Fs Model Only)

    5 - Installation tring protection fuses (-FS model only) izing of fuses Correctly sizing the string fuses to be used for protection against re- turn currents is very important since it can significantly reduce the risk of fire and damage to the PV generator. A “return current” can be generated in the event of a fault and relevant short-circuit at the ends of one or more PV modules of the system;...
  • Page 51 - Increase in Isc as a result of high temperature in the PV module - Thermal derating of the fuse - Maximum return current of the installed PV modules ABB can supply fuse kits of different values Code Description Quantity...
  • Page 52: Installation Procedure For Quick Fit Connectors

    5 - Installation nstallation procedure for quick fit connectors On inverter models with which quick fit connectors are supplied, they may be supplied in two different types: CAUTION: To avoid damage to the equipment, when attaching cables, pay particular atten- tion to polarity.
  • Page 53 5 - Installation MULTICONTACT (or equivalents) Installation of Multicontact connectors requires crimping to be carried out with suitable equipment. - Strip the cable to which you want to apply the connector (after verifying that it complies with the connector limits) 4...6mm 5.5...9mm - Apply the terminal to the conductor using suitable crimping pliers...
  • Page 54: Grid Output Connection (Ac Side)

    The table shows the maximum length of the line conductor based on the cross-section of this conductor: Cross-section of the Maximum length of the line conductor (m) line conductor (mm PVI-6.0-TL-OUTD PVI-8.0-TL-OUTD PVI-10.0-TL-OUTD PVI-12.5-TL-OUTD 4 mm² 55 m 43 m 34 m 28 m* 6 mm²...
  • Page 55: Load Protection Switch (Ac Disconnect Switch)

    To protect the AC connection line of the inverter, we recommend install- ing a device for protection against over current and leakage with the fol- lowing characteristics: PVI-6.0-TL-OUTD PVI-8.0-TL-OUTD PVI-10.0-TL-OUTD PVI-12.5-TL-OUTD Type Automatic circuit breaker with differential thermal magnetic protection Voltage rating...
  • Page 56: Communication And Control Board

    5 - Installation ommunication and control board Ref. Ref. Description inverter manual ALARM Connection to the multi-function relay (ALARM) REMOTE Connection to the remote ON/OFF (REMOTE) RS485 Connection of the RS485 (PC) line (RS485) RS485 (A) Connection of the RS485 (PC) line on RJ45 connector RS485 (B) Connection of the RS485 (PC) line on RJ45 connector 120 Ω...
  • Page 57: Connections To The Communication And Control Board

    5 - Installation onnections to the communication and control board Each cable which must be connected to the communication and control board must pass through one of the five service cable glands. • An M20 that takes cables from 7 mm to 13 mm in diameter. Gaskets with two holes are supplied as standard to insert into the cable gland, which enables two separate cables of a maximum cross-section of 5 mm to be accommodated.
  • Page 58: Serial Connection Communication (Rs485)

    5 - Installation erial Connection Communication (RS485) On the inverter there is a RS485 communication line, dedicated to con- necting the inverter to monitoring devices or to carrying out “daisy-chain” (“in-out”) connections of multiple inverters. The line may also be used to store settings with the dedicated advanced configuration software.
  • Page 59: Procedure For Connection To A Monitoring System

    5 - Installation rocedure for connection to a monitoring system Connect all the units of the RS485 chain in accordance with the “daisy- chain” arrangement (“in-out”) observing the correspondence between signals, and activate the termination resistance of the communication line in the last element of the chain by switching switch (to ON posi- tion).
  • Page 60: Remote Control Connection

    5 - Installation emote control connection The connection and disconnection of the inverter to and from the grid can be controlled through an external control. The function must be enabled in the relevant menu. If the Remote control function is disabled, the switching on of the inverter is dictated by the presence of the normal parameters that allow the inverter to connect to the grid.
  • Page 61: Nstruments

    - there are doubts or contradictions between your experience, the manual and/or other operators. ABB cannot be held responsible for damage to the equipment or the operator if it is the result of incompetence, insufficient qualifications or lack of training.
  • Page 62: Description Of Keyboard And Led Panel

    6 - Instruments escription of keyboard and LED Panel Using the combination of keyboard keys, under the display, it is possible to set values or scroll through the data items to view them. LED indica- tors are located alongside the keyboard, indicating the operating state of the inverter.
  • Page 63: Peration

    Operation eneral conditions Before checking the operation of the equipment, it is necessary to have a thorough knowledge of the INSTRUMENTS chapter and the functions that have been enabled in the installation. The equipment operates automatically without the aid of an operator; operating state is controlled through the instruments.
  • Page 64: Monitoring And Data Transmission

    • LCD display for displaying operating data • Data transmission on the dedicated RS-485 serial line. Data may be collected by a PC or a data logger with an RS-485 port. Contact the ABB support service with any queries about device compatibility.
  • Page 65: Commissioning

    After the grid standard was set you have 24 hours to make any changes to the grid standard value; 24 hours later the “Country Select.” functionality will be blocked, and any subsequent changes can only be made using a password provided on request by ABB. • After you have set the “Country” value, the message “Inizializing...Plea- se Wait”...
  • Page 66 7 - Operation • During the grid voltage check and measurement of the insulation re- sistance, the values for the grid voltage and frequency and the insula- tion resistance measured by the inverter are shown on the display. The inverter completes parallel connection with the grid SOLELY if the grid parameters meet the ranges provided for by the regulations in force and if the insulation resistance is greater than 1Mohm.
  • Page 67: Display Access And Settings

    7 - Operation isplay access and settings Once the inverter has been commissioned, it is possible/necessary to configure the inverter by accessing the Settings Menu directly from the display. The following are the main adjustable parameters (see the sec- tion on “Menu descriptions”) •...
  • Page 68: Led Behaviour

    7 - Operation ED behaviour = LED On The following table shows all the possible activation combinations of LEDs = LED flashing on the LED panel according to the operating status of the inverter. = LED Off = Any one of the conditions described above LED status Operating state...
  • Page 69: Specifications On The Operation Of The Leds

    7 - Operation pecifications on the operation of the LEDs In correspondence to each status of the inverter indicated by the constant or intermittent lighting of the specific LED, the display also shows a message identifying the operation which is being carried out or the defect/anomaly recorded (see specific chapter).
  • Page 70: Description Of The Menus

    7 - Operation escription of the menus The inverters are equipped with a graphic Display , consisting of 2 lines of 16 characters each, which can be used to: • Display the operating state of the inverter and the statistical data •...
  • Page 71 Lun 22 Lug 15:55 Lun 22 Lug 15:55 DOWN DOWN Type: Outdoor inverter type (OUTD) Type OUTD P/N: ABB product identification code P/N -3xxx- DOWN S/N: Sequential serial number S/N XXXXXX FW rel. : Firmware version installed FW rel. XXXX...
  • Page 72: Statistics Menu

    7 - Operation tatistics Menu Selecting STATISTICS from the three main sub-menus gives access to: Statistics ENTER Lifetime DOWN Partial DOWN Today DOWN Last 7 days DOWN Last month DOWN Last 30 days DOWN Last 365 days DOWN User Period 1.
  • Page 73 7 - Operation 4. Last 7 days This section of the menu displays the statistics for the last 7 days: • E-7d: Energy produced over the last 7 days • Val. : Value of production over the last 7 days, calculated using the cur- rency and conversion coefficient set in the relevant section of the SET- TINGS menu •...
  • Page 74: Settings Menu

    7 - Operation ettings Menu Selecting SETTINGS from the three main sub-menus brings up the first screen, asking for the password. The default password is "0000". This can be changed by using the display buttons, following the same procedure as always: •...
  • Page 75 7 - Operation 1. Address This section of the menu allows you to set the serial port addresses of the individual inverters connected to the RS485 line. The addresses that can be assigned are 2 to 63. The UP and DOWN buttons scroll through the numerical scale.
  • Page 76 7 - Operation The table below shows the parameters that can be changed and the range of values that may be set for each: Parameter Description Setting range Set U>> Grid over-voltage (OV) threshold (extended range) Unom … Unom x 1.3 Set U<<...
  • Page 77 We advise changing the activation voltage only if really necessary and to set it to the correct value: the photovoltaic generator sizing tool available on the ABB website will indicate whe- ther Vstart needs changing and what value to set it at.
  • Page 78 7 - Operation 10. Alarm This section of the menu allows you to set the activation status of a relay (available either as contact normally open – N.O. – or as contact normally closed – N.C.). This contact can be used, for example, to: activate a siren or a visual alarm, control the disconnect device of an external transformer, or control an external device.
  • Page 79 7 - Operation • Configurable alarm with reset at the end of the alarm signalling INVERTER RUN process (display text “Alarm Conf.”) N.C. The relay is activated (state: switched) whenever an error is present Relay State: Idle N.O. (code Exxx) or a warning (code Wxxx) from those selected from the list in the dedicated submenu.
  • Page 80 Under Voltage limit (set at 70% of Vstart). ABB sets the time at 60 sec. The user can set it at any time from 1 to 3600 sec.
  • Page 81 7 - Operation 14. Reactive power This section of the menu may be used to manage the supply of reactive power into the grid. There are 5 possible types of management: • No regulation: no regulation of reactive power. To enable this mode, select Enable and then OK (using the UP / DOWN arrows) •...
  • Page 82: Info Menu

    7 - Operation nfo Menu Selecting INFO from the three main sub-menus gives access to: Information ENTER Product ID DOWN Serial No DOWN Firmware DOWN Country Select. 1. Part No. Displays the model code. 2. Serial No. Displays the serial number and week and year of manufacture of the equipment .
  • Page 83: Autotest Procedure In Accordance With Standard Cei 0-21

    7 - Operation UTOTEST procedure in accordance with standard CEI 0-21 The autotest run in accordance with grid standard CEI-021 may be initia- ted from the display menu or by using an RS485/USB converter with the dedicated interface software (Aurora Communicator). The conditions required to perform an Autotest are: •...
  • Page 84 7 - Operation Test in corso The display shows the message “Performing Test” when the test has ..started. At the end of the test, when the inverter has disconnected from the grid, the results and values of the test performed will appear on the display. You can move from one screen to another using the UP/DOWN arrow keys.
  • Page 85: Aintenance

    Maintenance eneral conditions Checking and maintenance operations must be carried out by specialized staff assigned to carry out this work. Maintenance operations must be performed with the apparatus disconnected from the grid (power switch open) and the photovoltaic panels obscured or isolated, unless otherwise in- dicated.
  • Page 86: Routine Maintenance

    PV plant. We recommend that maintenance operations be carried out by qualified personnel or by the personnel of ABB (as set forth in a maintenance contract). The periodicity of the maintenance operations may vary in accordance with local environmen-...
  • Page 87 8 - Maintenance - Code on display - Error message Name of Alarm and Cause Solution - Signal • Measure the insulation resistance using a megohmmeter posi- tioned in the photovoltaic field (positive terminal short-circuited at the negative pole) compared to ground. The measurement is strongly influenced by the environmental conditions, so must be - No code Ground fault of photovoltaic generator:...
  • Page 88 8 - Maintenance - Code on display - Error message Name of Alarm and Cause Solution - Signal - W010 * - Fan broken! Fan broken: • Error inside the inverter and cannot be checked externally. Yellow LED lamp. This error occurs when there is a malfunction in the fan/ - If the alarm repeats persistently, contact customer assistance.
  • Page 89 8 - Maintenance - Code on display - Error message Name of Alarm and Cause Solution - Signal • Check whether the composition of the PV generator enables Input over-current (photovoltaic generator): - E001 input current which exceeds the maximum threshold allowed by The alarm occurs when the inverter's input current - Input OC the inverter and that the configuration of the inputs (independent...
  • Page 90 8 - Maintenance - Code on display - Error message Name of Alarm and Cause Solution - Signal • Check that the setting of the "IN MODE" switch is specifically Incorrect configuration of inputs (set in parallel ra- set to "PAR" and that the bridges between the two input channels ther than independent): have been included.
  • Page 91 8 - Maintenance - Code on display - Error message Name of Alarm and Cause Solution - Signal Failure of the test on the inverter's relay (DC-AC cir- cuit): Before connecting to the grid the inverter carries out in- • Error inside the inverter and cannot be checked externally. - E021 ternal tests.
  • Page 92 8 - Maintenance - Code on display - Error message Name of Alarm and Cause Solution - Signal High leakage current (DC side): Error in the internal measurement (made when the in- - E030 verter is grid connected) of the leakage current of the •...
  • Page 93: Power Limitation Messages

    8 - Maintenance - Code on display - Error message Name of Alarm and Cause Solution - Signal • Check that the inverter is not exposed to direct sunlight. Wait for Excessive temperature measured inside the inver- E056 the temperatures to which the inverter is exposed to return to the ter's wiring box: - Over Temp.
  • Page 94 8 - Maintenance - Message on display Name of Derating and Cause Solution - Signal Power limitation for over-voltage: The message indicates that the user has set a power limitation due to over voltage (parameter U >(10 min)) in order to reduce the maximum output power of the inverter when the reading of the - LIMxxx% CODE:02 average grid voltage exceeds certain limits.
  • Page 95: Registration On "Registration" Website And Calculation Of Second-Level Password (Service Menu)

    8 - Maintenance egistration on “Registration” website and calculation of second- level password (Service Menu) Settings In order to obtain the second-level password needed to access the in- verter's service menu, it is necessary to go through the following stages: ENTER Password 0000 ENTER...
  • Page 96 8 - Maintenance Stage 3 - Request for second level password - Go online and access https://registration.abbsolarinverters.com - Insert the Username (corresponding to the email used during registra- tion) and the Password obtained at the end of Stage 2 - Access the section dedicated to requesting the second-level password - Choose the inverter model from the drop-down list and insert Update Ver., Serial Number and Week of Production of the inverter which were obtained previously (Stage 1)
  • Page 97 8 - Maintenance - Click on icon to request password. Should there be an error in inputting data, the fields containing the error will be highlighted in red. If, on the other hand, the data are correct, the passwords will be shown in a new window and at the same time sent to the email address used for registration.
  • Page 98: Resetting The Time Remaining To Change The Grid Standard

    8 - Maintenance esetting the time remaining to change the grid standard From the time a valid grid standard is entered and the inverter is turned on, a period of 24 hours is available to modify the grid standard setting. The 24 hours are counted only when the inverter is turned on.
  • Page 99: Replacing The Input Fuses (Version -Fs)

    8 - Maintenance eplacing the input fuses (version -FS) Using fuses with inappropriate specifications may irreparably damage the unit. Any conse- quential damage to the inverter is not covered by the warranty. In case of damage of one or more input fuses, the inverter (not being able to monitor the sta- tus of fuses) will continue to export energy to the grid without signaling any alarm.
  • Page 100: Models Equipped With Fuse Holder Extractors

    8 - Maintenance Depending on the presence of fuse holder extractors or safety caps, fol- low the corresponding procedure: odels equipped with fuse holder extractors 5a. Remove the fuse holder by pressing its handle. 6a. Extract the fuse to be replaced from the fuse holder by releasing the retaining clip.
  • Page 101: Replacement Of The Buffer Battery

    8 - Maintenance eplacement of the buffer battery Replacement of the buffer battery may be necessary in case of: 1. Error signal on display 2. Reset of the date and time settings The battery is of the CR2032 type and is installed on the motherboard Procedure to replace the buffer battery: 1.
  • Page 102: Verification Of Ground Leakage

    8 - Maintenance erification of ground leakage In the presence of anomalies or report of ground fault (where provided), there may be a ground leakage from the PV generator (DC side). To check this, measure the voltage between the positive pole and ground and between the negative pole (of the PV generator) and ground using a voltmeter whose input accepts a voltage sufficient for the dimensions of the photovoltaic generator.
  • Page 103: Behaviour Of A System With Leakage

    8 - Maintenance ehaviour of a system with leakage If the voltage measured between one of the two poles and ground does not tend to 0V and stabilizes on a value, there is a ground leakage from the PV generator. Example: When the measurement is made between positive pole and ground, a voltage of 200V is measured.
  • Page 104: Measuring The Insulation Resistance Of Photovoltaic Generator

    8 - Maintenance easuring the insulation resistance of photovoltaic generator To measure the insulation resistance of the PV generator compared to ground , the two poles of the PV generator must be short-circuited (using a suitably sized switch). Once the short-circuit has been made, measure the insulation resistance (Riso) using a megohmmeter positioned between the two shorted poles and ground (of the inverter).
  • Page 105: Storage And Dismantling

    ABB CANNOT be held responsible for disposal of the equipment: displays, cables, batteries, accumulators, etc., and therefore the customer must dispose of these substances, which are potentially harmful to the environment, in accordance with the regulations in force in the country of installation.
  • Page 106: Further Information

    For more information on ABB products and services for solar applica- tions, navigate to www.abb.com/solarinverters - 106 -...
  • Page 107: Contact Us

    www.abb.com/solarinverters...

This manual is also suitable for:

Pvi-6.0-tl-outdPvi-10.0-tl-outdPvi-12.5-tl-outd

Table of Contents