12
The commissioning data sheet is used to record the process and result of the commissioning.
Table 12-1 BTS commissioning data sheet
Site Name
BTS Model
Date and Time
Commissioning
Engineers
Commissioning
Mode
Commissioning
Result
Commissioning Item
Preparation for
BTS
Commissioning
Issue 03 (2008-07-15)
Data Sheet for Commissioning
口 Online Commissioning 口 Offline Commissioning
口 Successful 口 Failed
Faults in BTS hardware
installation cleared?
The BTS successfully powered
on?
Data configuration for BTS
commissioning in BSC available
on the Site Maintenance
Terminal PC?
Board software for upgrade
downloaded to the Site
Maintenance Terminal PC?