The Topology Management window is displayed, as shown in
Figure 8-6 Topology Management window
Step 6 Right-click a DRFU.
A shortcut menu is displayed.
Step 7 Choose Loop Test from the shortcut menu.
The sub-menu is displayed.
Step 8 Choose Path A or Path B.
The Loop Test dialog box is displayed.
Step 9 Click Start.
After the test is complete, the result is displayed on the status bar at the bottom of the dialog
box.
Step 10 Repeat
----End
Issue 03 (2008-07-15)
Step 5
through
Step 9
to perform the loopback test of all the DRFUs.