Installing The Cabinets - Huawei OptiX RTN 980 Quick Installation Manual

Radio transmission system v100
Hide thumbs Also See for OptiX RTN 980:
Table of Contents

Advertisement

2

Installing the Cabinets

a
Installing the Base
Cast a concrete pad.
The height of the concrete pad must meet the heat-dissipation and waterproofing requirements of the
cabinet. The concrete pad must be 200 mm higher than the ground, and the horizontal error must be less
than 5 mm when the pad is cast.
Mark the anchor points for the base.
Unit: mm
Drill the holes by using a hammer drill.
90°
Concrete pad
CAUTION
Do not use the base as a positioning tool when drilling. Otherwise, the paint on the base may be scratched.
Φ16
52-60 mm
Concrete pad
9