7.1 Checking Before Power-On

Table 7-1 Checklist
No.
1
2
3
4
5
6
7
8
9
Issue 01 (2021-04-05)
Check Item
SUN2000 installation
Smart Dongle
Cable routing
Cable ties
Reliable grounding
Switch
Cable connection
Unused terminals and ports
Installation environment
Copyright © Huawei Technologies Co., Ltd.
7

Commissioning

Acceptance Criteria
The SUN2000 is installed correctly and
securely.
The Smart Dongle is installed correctly and
securely.
The cables are routed properly as required
by the customer.
Cable ties are evenly distributed and no burr
exists.
The PE cable is connected correctly and
securely.
DC switches and all the switches connecting
to the SUN2000 are OFF.
The AC output power cable, and DC input
power cables are connected correctly and
securely.
Unused terminals and ports are locked by
watertight caps.
The installation space is proper, and the
installation environment is clean and tidy.