UPS5000-H-(400 kVA-600 kVA)
User Manual (100 kVA Power Module)
Figure 7-9 Starting a forced equalized charging test
----End
7.6.1.2 Performing a Shallow Discharge Test
Before performing a shallow discharge test, ensure that:
● The UPS works in normal mode with a load rate fluctuation less than 10%.
● The UPS generates no battery overtemperature, overvoltage, or overcurrent
● The mains, batteries, charger, and discharger are normal. No overload alarm is
Automatic Shallow Discharge Test
Step 1 On the home screen of the LCD, choose System Info > Settings > Battery
Settings and set Sched. shallow dis. test to Enable.
Step 2 Set Sched. shallow dis. test time and Sched. shallow dis. test interval as
required. After setting is complete, the system will perform an automatic shallow
discharge test based on the settings.
----End
Manual Shallow Discharge Test
Step 1 On the home screen of the LCD, choose System Info > Maintenance > Battery
Maint.
Issue 01 (2020-11-30)
NO TE
The forced equalized charging test automatically stops in any of the following cases:
● The test duration reaches the forced equalized charging protection time (12–24 h, 18 h
by default).
● The UPS generates a battery overtemperature, overvoltage, or overcurrent alarm.
● An alarm is generated.
NO TICE
alarm. No generator is connected to the UPS.
generated.
Copyright © Huawei Technologies Co., Ltd.
7 System Commissioning
78