6.1.1.2 Installation Clearances
Figure 6-1 UPS dimensions
Reserve the following clearances around the cabinet to facilitate operations and
ventilation:
●
●
●
●
6.1.2 Tools and Instruments
● Use insulated tools to avoid electric shocks.
● The following table lists only the common tools for installation and cable
Issue 01 (2020-11-30)
Reserve a clearance of at least 950 mm from the front of the cabinet for
ventilation and operations.
Reserve a clearance of at least 500 mm from the top of the cabinet for
operations.
Reserve a clearance of at least 500 mm from the rear of the cabinet for
ventilation.
Reserve a clearance of at least 800 mm if you need to perform operations at
the rear of the cabinet.
NO TICE
connection. For more dedicated tools required, see the document for each
component. Prepare tools based on site requirements.
Copyright © Huawei Technologies Co., Ltd.
6 Installation
49