Huawei IDS2000 Installation Manual

Intelligent micro-modular data center 2000 mm high cabinet in dual-row aisle containment
Hide thumbs Also See for IDS2000:
Table of Contents

Advertisement

Quick Links

IDS2000 Intelligent Micro-Modular Data Center
V500R001
Installation Guide (2000 mm
High Cabinet in Dual-Row Aisle
Containment)
Issue
Draft A
Date
2015-06-29
HUAWEI TECHNOLOGIES CO., LTD.

Advertisement

Table of Contents
loading

Summary of Contents for Huawei IDS2000

  • Page 1 IDS2000 Intelligent Micro-Modular Data Center V500R001 Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) Issue Draft A Date 2015-06-29 HUAWEI TECHNOLOGIES CO., LTD.
  • Page 2 Notice The purchased products, services and features are stipulated by the contract made between Huawei and the customer. All or part of the products, services and features described in this document may not be within the purchase scope or the usage scope. Unless otherwise specified in the contract, all statements, information, and recommendations in this document are provided "AS IS"...
  • Page 3: About This Document

    Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) About This Document About This Document Purpose This document describes how to install the IDS2000 intelligent micro-module in the double-row aisle containment scenario. Intended Audience This document is intended for: ...
  • Page 4 IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) About This Document Symbol Description NOTE is used to address information not related to personal injury, equipment damage, and environment deterioration. Change History Changes between document issues are cumulative. The latest document issue contains all updates made in previous issues.
  • Page 5: Table Of Contents

    IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) Contents Contents About This Document ........................ii 1 Precautions ............................. 1 1.1 General Safety Precautions ............................1 1.2 Electrical Safety ................................2 1.3 Battery ..................................4 1.4 Mechanical Safety ................................
  • Page 6 IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) Contents 4.5.1 Cabinet Installation Flowchart ..........................34 4.5.2 Removing the Pallet from a 2000 mm High Cabinet ....................34 4.5.3 Placing the Cabinet ..............................35 4.5.4 Securing a Cabinet ..............................
  • Page 7 IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) Contents 4.11.2 Installing the Server ............................. 117 4.11.3 Installing a LAN Switch ............................119 4.11.4 Installing an ECC Collector ..........................121 4.11.5 (Optional) Installing the VCN500 ........................121 4.11.6 Installing a Skylight Controller ..........................
  • Page 8 IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) Contents 4.12.12.13 Connecting a Cable to the WLDS900 Water Detector .................. 172 4.12.12.14 Connecting a Cable to a Temperature Sensor ....................172 4.12.12.15 Connecting a Monitoring Cable to the MS899 Electronic Lock ..............173 4.12.12.16 Connecting a Monitoring Cable to a PDU2000 ....................
  • Page 9: Precautions

    Only trained and qualified personnel are allowed to remove safety facilities and inspect the equipment.  Only personnel certified or authorized by Huawei are allowed to replace or change the equipment or components (including software).  Installation personnel must report faults or errors that might cause serious safety issues to related owners.
  • Page 10: Electrical Safety

    IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 1 Precautions Grounding Requirements Equipment to be grounded must meet the following requirements:  When installing the equipment, always ground the device first. Disconnect the ground cable at the end of removing the device.
  • Page 11 IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 1 Precautions Ground the device before powering it on. Otherwise, personal injury or device damage may be caused by high leakage current. If a "high electrical leakage" tag is present on the power terminal of the device, you must ground the device before powering it on.
  • Page 12: Battery

    IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 1 Precautions Figure 1-1 Putting on an ESD wrist strap 1.3 Battery This section describes precautions for operating batteries. Before operating batteries, carefully read the safety precautions for battery handling and connection.
  • Page 13 IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 1 Precautions Battery short circuits may cause human injuries. Although the voltage of ordinary batteries is low, the instantaneous high current caused by the short circuit releases a great deal of energy.
  • Page 14: Mechanical Safety

    IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 1 Precautions If your body meets the acid, wash the part that has met the acid with clean water immediately, or immediately call a doctor if the situation is serious.
  • Page 15: Others

    IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 1 Precautions  Be careful to prevent injury when moving heavy objects.  To prevent injury, when moving the chassis outwards, be aware of unfixed or heavy objects on the chassis.
  • Page 16: Installation Preparations

    IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 2 Installation Preparations Installation Preparations 2.1 Transportation Precautions Air Conditioner Transportation Precautions  Only trained personnel are allowed to move the cabinet. Use a pallet truck to transport the cabinet secured to a wooden support to the installation position.
  • Page 17: Unpacking And Acceptance

    IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 2 Installation Preparations 2.2 Unpacking and Acceptance Context Unpack and inspect all cabinets, mechanical parts, and components. Check that all the items are intact and comply with the packing list on the presence of both the project supervisor and customer.
  • Page 18 IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 2 Installation Preparations Check Item Requirement Check Result kN/m  Standard live load of the monitoring center: 6 kN/m □ Compliant □ Equipment room net For detailed requirements, see 2.4 Site...
  • Page 19: Site Requirements

    One skylight controller dry contact: Connects to the fire extinguishing system to link the fire Incompliant extinguishing system and the skylights If any of the requirements is not met, contact Huawei technical support. 2.4 Site Requirements Equipment Room Height Requirement Figure 2-2 shows the heights of modules with 2000 mm high cabinets in dual-row aisle containment.
  • Page 20 IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 2 Installation Preparations Figure 2-2 Height of a module in 2000 mm scenario (unit: mm) (1) The maximum height of a module (2) The maximum height of a module with...
  • Page 21: Documents

    IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 2 Installation Preparations Figure 2-3 Equipment room space requirements (unit: mm) 2.5 Documents Before the installation, get familiar with the following documents. Table 2-3 Documents for hardware installation...
  • Page 22: Tools And Instruments

    IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 2 Installation Preparations Document Function Obtaining Method (Remarks) into the (For Customer) iManager NetEco Product Documentation (V600R007C00) (HDX)_EN. ECC500 V600R001C00 Describes the overview of Downloaded from...
  • Page 23 IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 2 Installation Preparations Name, Specifications, and Appearance Adjustable wrench Socket wrench (M6, Hex key Box-end wrench (6") M8, and M12) (M6, M8, and M12) Hand drill (Φ3, Hammer drill (Φ16...
  • Page 24: Personnel Requirements

    Only trained and qualified personnel who fully understand basic safety precautions are allowed to install and operate a modular data center. Huawei will not be liable for any consequence caused by the violation of this document. The requirements are as follows:...
  • Page 25 Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 2 Installation Preparations  Customers' installation personnel must be trained by Huawei and understand how to install and operate a modular data center.  The number of installation personnel varies depending on the project progress and the installation environment.
  • Page 26: Scenario

    IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 3 Scenario Scenario Figure 3-1 shows the floor plan of a modular data center with an integrated PDU8000. Figure shows the exterior of a micro-module.
  • Page 27 IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 3 Scenario Figure 3-2 Exterior (1) Skylight (2) Cable tray (3) End door (4) Base (5) Cabinet (6) Cable trough Issue Draft A (2015-06-29) Huawei Proprietary and Confidential...
  • Page 28: Hardware Installation

    IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation Hardware Installation 4.1 Installation Flowchart Figure 4-1 shows the installation flowchart. Issue Draft A (2015-06-29) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 29 IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation Figure 4-1 Installation flowchart Issue Draft A (2015-06-29) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 30: Positioning Cabinets Or Bases

    IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation 4.2 Positioning Cabinets or Bases Prerequisites You have obtained the engineering layout diagram. Cabinet Positioning Method Cabinets can be positioned using each a marker or a laser locator.
  • Page 31: Installing Bases

    IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation Step 3 If a base needs to be installed, mark the anchoring holes and position the base according to distances between cabinet anchoring points indicated in the following figure.
  • Page 32: Placing Bases

    IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation Install the base decorative plates for array cabinets only after other components such as pipes and cables are properly connected; otherwise, you may need to rework when a component needs to go under a decorative plate.
  • Page 33: Deploying An 800 Mm Wide Fixed Base

    IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation 4.3.2.2 Deploying an 800 mm Wide Fixed Base Context An 800 mm wide fixed base has a BOM number of 21151125 and applies to 800 mm network cabling cabinets.
  • Page 34 IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation Figure 4-7 PDU8000 base (unit: mm) Procedure Step 1 Unscrew the four M6 screws and remove the adjustable feet from the base, as shown in Figure 4-8.
  • Page 35: Deploying A 300 Mm Wide Fixed Base

    IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation 4.3.2.4 Deploying a 300 mm Wide Fixed Base Context A 300 mm wide fixed base has a BOM number of 21152146 and applies to 300 mm wide air conditioners.
  • Page 36 IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation Figure 4-10 Drilling a hole (unit: mm) Step 5 Measure the hole depths and distances. If any deviation is found, mark the positions again and drill new holes.
  • Page 37 IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation Figure 4-12 Tightening expansion bolts Step 8 Secure the base to an adjacent base using two M8 screws and nuts, as shown in Figure 4-13.
  • Page 38: Routing And Securing Air Conditioner Pipes

    IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation 4.4 Routing and Securing Air Conditioner Pipes 4.4.1 Requirements of Air Conditioner Pipe Connectors and Water Quality Preparing the Water Inlet Pipe for a Netcol5000-A020 Humidifier The humidifier water inlet pipe can be connected in two methods: ...
  • Page 39 IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation Drainpipes should be able to withstand a temperature greater than 100º C; otherwise, pipe deformation may occur (for equipment configured with a humidifier).
  • Page 40: Precautions For Routing And Securing Air Conditioner Pipes

    IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation If the inlet water contains large granules, install a water filtering device at the inlet port to prevent pipe blockage. Table 4-1 describes the NetCol5000-A water quality requirements.
  • Page 41 IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation Figure 4-16 Pipe supports (unit: mm)  The height of a U-shaped pipe clamp equals to the pipe diameter with thermal insulation foam minus 5 mm.
  • Page 42: Installing The Cabinet

    IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation 4.5 Installing the Cabinet 4.5.1 Cabinet Installation Flowchart Figure 4-18 Cabinet installation flowchart 4.5.2 Removing the Pallet from a 2000 mm High Cabinet Context ...
  • Page 43: Placing The Cabinet

    IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation Do not damage the cabinet exterior. Step 2 Remove the screws that secure the cabinet and the pallets, as shown by (1) in Figure 4-19.
  • Page 44: Securing A Cabinet

    IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation  Measure the aisle width between cabinet doors using a measuring tape.  If the aisle width is not 1200 mm, adjust the cabinet positions to ensure a 1200 mm wide aisle.
  • Page 45: Securing A Server Cabinet

    IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation Figure 4-21 Securing a PDU8000 ----End 4.5.4.2 Securing a Server Cabinet Procedure Step 1 Adjust the anchor bolts to increase the cabinet height to 2000 mm.
  • Page 46: Securing A Netcol5000-A020 Air Conditioner

    IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation Figure 4-22 Securing a cabinet Step 4 Secure other cabinets in the same manner. ----End 4.5.4.3 Securing a NetCol5000-A020 Air Conditioner Procedure Step 1 Place a NetCol5000-A020 onto a base and adjust its position.
  • Page 47 IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation Figure 4-23 Placing the air conditioner onto a base Step 2 Installing enclosure frames for half-sized NetCol5000-A020 air conditioners. The BOM number is 52271152. Fix enclosure frames onto the front door frame using six M6 screws...
  • Page 48 IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation Figure 4-24 Installing an enclosure frame Step 3 Install the front door to the enclosure frame and connect the ground cable under the front door to the enclosure frame according to the label on the enclosure frame.
  • Page 49: Installing Adaptive Frames

    IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation Figure 4-25 Securing air conditioners and bases ----End 4.5.5 Installing Adaptive Frames 4.5.5.1 Installing the PDU8000 Tail Frame Context A PDU8000 tail frame is used to increase the depth of a PDU8000 to 1200 mm. Its BOM number is 21500952.
  • Page 50 IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation Step 2 Remove the PDU8000 rear door, bolt fixing plate, rear door mounting kit, connection plates, and ground screws. Put aside the removed bolt fixing plate, rear door mounting kit, connection plates, and ground screws.
  • Page 51 IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation Figure 4-28 Securing the tail frame Step 4 Install bolt fixing plate, rear door mounting kit, connection plates, and ground screws on the corresponding positions on the tail frame.
  • Page 52: Installing A 300 Mm Wide Air Conditioner Adaptive Frame

    IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation Figure 4-29 PDU8000 with a tail frame ----End 4.5.5.2 Installing a 300 mm Wide Air Conditioner Adaptive Frame Context  If an odd number of 300 mm wide air conditioners are installed, the adaptive frame needs to be installed so that the lengths of the two cabinet rows are the same.
  • Page 53 IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation Figure 4-30 Combining the adaptive frame with the cabinets Do not tighten the top panel of the adaptive frame too much. Otherwise, the top panel will be uneven.
  • Page 54: Combining Cabinets

    IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation Figure 4-31 Installing the adaptive frame top panel Step 4 Install the rear panel of the adaptive frame in the same way described in...
  • Page 55: Installing Cabinet Accessories

    IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation Open the front and rear doors. Wrench the anchor bolts using an adjustable wrench to adjust the cabinet height, as shown by (1) in Figure 4-32.
  • Page 56 IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation Figure 4-33 Taking out PDU2000 industrial connectors Step 2 Lay out the PDU2000 industrial connectors and cables on the cabinet top, and close and lock...
  • Page 57: Optional) Installing A Branch Ground Bar

    IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation Follow-up Procedure Before connecting the power plug of a device to the PDU2000, loosen the locking device on the PDU2000. After connecting the power plug, tighten the locking device.
  • Page 58: Installing The Contained Aisles

    IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation Figure 4-36 Installing a ground bar ----End 4.6 Installing the Contained Aisles 4.6.1 Installation Flowchart Figure 4-37 shows the flowchart for installing dual row aisle containment.
  • Page 59 IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation Figure 4-38 600 mm wide control skylight (1) Control skylight plate (2) Skylight connective plates Figure 4-39 600 mm wide flat skylight...
  • Page 60 IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation Figure 4-40 600 mm wide rotating skylight (1) Rotating skylight plate (2) Skylight connective plates (3) Magnetic lock The BOM number of rotating and flat skylights is the same. A rotating skylight requires a magnetic lock but a flat skylight does not.
  • Page 61 IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation Figure 4-42 300 mm wide flat skylight (1) Flat skylight plate (2) Skylight connective plates A skylight in the package is folded. To expand the skylight, draw out the spring pin, rotate a connective plate by 90 degrees, release the spring pin, and insert the pin into the hole in the side plate to prevent side plate rotation.
  • Page 62: Installing Skylights

    IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation Skylight Type Specifications BOM Number Layout Sequence (Width) alternately. Two 300 mm 21501040 rotating skylights cannot be installed together.  A rotating...
  • Page 63 IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation Procedure Step 1 Install control, flat, and rotating skylights based on the skylight layout.  Install a control skylight: A skylight in the package is folded. Rotate the skylight connective plates to expand the skylight in a door structure.
  • Page 64 IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation  When securing the skylight, place the spring pins in the lower right corner of the skylight connective plates into holes on the top of cabinets to prevent skylight rotation during bolt tightening.
  • Page 65 IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation  When securing the skylight, place the spring pins in the lower right corner of the skylight connective plates into holes on the top of cabinets to prevent skylight rotation during bolt tightening.
  • Page 66 IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation Secure the fastener you removed to the magnetic lock using M6x16 screws, as shown in Figure 4-49. The magnetic lock installed in this step is separately numbered (BOM number: 02070140) and delivered.
  • Page 67: Installing End Doors

    IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation Figure 4-51 Securing the electromagnet Step 2 Secure adjacent skylight connective plates using four M6x16 screws, as shown in Figure 4-52. When securing adjacent skylights, keep the skylight plates flush with each other.
  • Page 68: Installing A Sliding Door

    IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation Check Item Result between the cabinet top and the floor surface is 2000 mm ± 1 mm. □ Compliant □ Incompliant The distance between cabinet front doors on both sides of an aisle is 1200 mm ±...
  • Page 69 IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation Figure 4-54 Assembling the front and rear sealing plates Figure 4-55 Securing the side sealing plate Procedure Step 1 Take out five components from the package and assemble every two components into front...
  • Page 70 IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation Figure 4-56 Front and rear sealing plates before and after assembly Step 2 Secure the assembled front and rear sealing plates to the cabinets using two M6x16 screws...
  • Page 71: Installing A Sliding Door In The 2000 Mm Scenario

    IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation Figure 4-58 Securing the side sealing plate ----End 4.6.4.1.2 Installing a Sliding Door in the 2000 mm Scenario Context Figure 4-59 shows the components of a sliding door. Its BOM number is 21501041.
  • Page 72 IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation Name Quantity Remarks (2) Mounting kit under the Two groups sliding door (3) Damper 2 PCS Interface between the door and cabinet...
  • Page 73 IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation Figure 4-61 Securing a guide rail Step 3 Install the top frame for a sliding door for 2000 mm high cabinets, as shown by 1 in Figure 4-62.
  • Page 74 IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation Figure 4-63 Adjusting a hanging wheel Push the sliding door onto the guide rail and dampers, as shown in Figure 4-64. Issue Draft A (2015-06-29) Huawei Proprietary and Confidential Copyright ©...
  • Page 75 IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation  When pushing the sliding door onto a damper, lift the door to lock the bottom channels into the damper.  The brush located on the interior of the sliding door is used to seal the gap between the sliding door and cabinets.
  • Page 76 IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation Symptom Cause Adjustment Basic Method Requirements top of the right door right door panel panel. counterclockwise, or rotate the internal hanging wheel of the right door panel clockwise.
  • Page 77 IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation Figure 4-66 Inserting a pad Step 6 Install barrier kits on the guide rail, as shown in Figure 4-67. Secure barrier kits using the delivered screws.
  • Page 78: Installing A Double Revolving Door (Compatible With Access Control Components)

    IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation 4.6.4.2 Installing a Double Revolving Door (Compatible with Access Control Components) Double Revolving Door Figure 4-68 shows the components of a double revolving door. BOM numbers of double revolving door components: ...
  • Page 79 IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation Procedure Step 1 Assemble the front, rear, and side sealing plates of an end cabinet into frames, and partially secure them by using M6x16 screw assemblies.
  • Page 80: Installing A Door Frame

    IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation 4.6.4.2.2 Installing a Door Frame Procedure Step 1 Assemble a door frame. When an audible and visual alarm is triggered, the alarm needs to be immediately noticed by someone who enters the equipment room.
  • Page 81 IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation Figure 4-71 Assembling a door frame Step 2 Install a door frame. Attach a door frame to the cabinets. Partially secure a door post to a skylight side panel using two M6x16 screws and nuts. A total of four M4 screws and nuts are used to secure the two posts.
  • Page 82 IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation Figure 4-72 Installing a door frame Put M6x16 screws through the fixing plate, as shown by (3) in Figure 4-71. Then secure...
  • Page 83: Installing Door Panels

    IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation  Adjust the anchor bolts to make it level if possible.  Insert one pad (0.6 mm thick) delivered with the product under the door post.
  • Page 84 IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation Figure 4-74 Securing a door panel to each post using hinges It is recommended that you install hinges from the top to the bottom.
  • Page 85 IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation  If the door tilts by a large degree, adjust the anchor bolt of the cabinet. If a post is lifted off the floor due to the adjustment, add spacers under the post.
  • Page 86 IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation Figure 4-76 Door panel tilting down If door panels mismatch, you can adjust the fastening screws between the posts and cabinets or between the posts and skylight connective plates, and insert spacers so that...
  • Page 87: Installing A Door Closer

    IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation 4.6.4.2.4 Installing a Door Closer Procedure Step 1 Install guide rails for a door closer. Remove the rear panel from the upper frame mounting kit, as shown by (1) in Figure 4-79.
  • Page 88 IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation Avoid striking with a hard object when mounting the closer on the top of the door panel into the square hole in the closer arm. If the arm does not fit easily, strike with a rubber mallet to install the closer arm in position.
  • Page 89 IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation  Properly hold the door closer arm when installing or removing it to prevent it from bouncing due to the pretightening force from the closer.
  • Page 90 IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation Step 5 Adjust the door opening angle and closing speed based on actual requirements. In Figure 4-84, the left figure is the top view of the door when it is opened to the left by 90 degrees, and the right figure shows two openness ranges in which the door rotation speed can be adjusted.
  • Page 91: Installing Post Side Panels And Removing The Auxiliary Bar

    IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation The screw can only be adjusted slightly. Otherwise, the closer will fail to work due to oil leakage. Move the door for five consecutive times to ensure that the door can properly move back to the original position.
  • Page 92: Installing Cable Trays

    IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation 4.7 Installing Cable Trays Context A 390 mm high cable tray is used to route cables across an aisle. Its BOM number is 21151136.
  • Page 93 IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation Figure 4-87 Installing a fixing plate There is no need to remove the two screws if they are not installed. Step 2 Secure the delivered base to the fixing plate using M8x20 bolt assemblies, as shown in Figure 4-88.
  • Page 94 IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation Figure 4-89 Installing a conversion bracket Figure 4-90 Installed cable tray (unit: mm) Ensure that the front of the cable ladder is 535 mm away from the front of the base, as shown in Figure 4-90.
  • Page 95: Installing Cable Troughs

    IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation Figure 4-91 Connecting ground cables from the cable ladder and base to the cabinet Figure 4-92 Cabinet ground points ----End 4.8 Installing Cable Troughs This section describes the positions and methods for installing cable troughs.
  • Page 96: Installing A 600 Mm Wide Cable Trough

    IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation 4.8.1 Installing a 600 mm Wide Cable Trough Context Install two 600 mm cable troughs on the top of every 600 mm wide cabinet. Install two cable troughs on the top of PDU8000s first, and then install cable troughs on the top of other cabinets along the aisle in sequence.
  • Page 97 IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation Figure 4-94 PDU2000 cable routing on the top of a cabinet (1) Weak-current cable trough (2) Strong-current cable trough Procedure Step 1 Keep a vertical plate of the cable trough flush with the top surface of the cabinet and clamp...
  • Page 98 IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation Figure 4-96 Rotating the vertical plate by 90 degrees Step 3 Install the other vertical plate in the eighth square hole counting from the clamping position of the first vertical plate in the same way.
  • Page 99 IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation Figure 4-98 Installing a supporting plate Step 5 Install a partition plate. Press both sides of the V-shaped partition plate with hands to decrease...
  • Page 100 IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation Figure 4-100 Installing an interconnecting wrench (1) Interconnecting wrench Step 7 Install cable troughs at intervals of 117 mm (a distance of five square holes) above the rear...
  • Page 101: Installing A 300 Mm Wide Cable Trough

    IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation 4.8.2 Installing a 300 mm Wide Cable Trough Context A 300 mm wide cable trough is installed on the top of a 300 mm wide cabinet after a 600 mm wide cable trough is installed.
  • Page 102: Installing An 800 Mm Wide Cable Trough

    IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation Figure 4-103 Connecting a 300 mm wide cable trough to a 600 mm wide cable trough (1) Interconnecting wrench ----End 4.8.3 Installing an 800 mm Wide Cable Trough An 800 mm wide cable trough is installed on the top of an 800 mm wide cabinet.
  • Page 103: Optional) Installing The Access Control System

    IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation Procedure Step 1 Hold the top of the end panels with both hands to keep it vertical. Press it from up to down into the hooks at the end of the cable troughs until the top of the end panels aligns with the top of the cable troughs.
  • Page 104: Installing A Double-Door Magnetic Lock

    IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation Figure 4-105 Layout of access control components (1) Audible and visual alarm (2) Card reader (3) Emergency door release button (4) Lighting switch...
  • Page 105 IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation Figure 4-106 Removing the top plate from a double-door magnetic lock base Remove the fixing plate from the magnetic lock using the hex key delivered with the magnetic lock.
  • Page 106 IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation Figure 4-108 Securing the fixing plate to a double-door magnetic lock base Connect the cable from the magnetic lock to the upper frame mounting kit, and secure the magnetic lock to the fixing plate using the hex key.
  • Page 107 IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation Figure 4-110 Installing the bottom plate of a double-door magnetic lock base Step 2 Install the top plate of a double-door magnetic lock base.
  • Page 108 IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation Figure 4-112 Assembling a magnet component Secure the magnet bases to the top of the double door panels. Figure 4-113 Installing a magnet base Secure one magnet base using two M4 pan head screw assemblies.
  • Page 109 IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation Figure 4-114 Installing a magnet Step 4 Commission the magnet. If the magnet does not work properly after power-on, check the following items: Check whether the magnet provides magnetic force by attaching magnetizable iron parts to them.
  • Page 110: Installing The Card Reader

    IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation Figure 4-115 Adjusting the gap between a magnetic lock and the magnet Figure 4-116 Spacer ----End 4.9.2 Installing the Card Reader Procedure Step 1 Unscrew and remove the cover from a card reader.
  • Page 111 IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation Figure 4-117 Removing the cover of a card reader Step 2 Remove the card reader mounting bracket from the door post. Before installing a card reader, remove the door post side panel. After the card reader is installed and cables are connected, reinstall the door post side panel.
  • Page 112 IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation Figure 4-118 Removing the card reader mounting bracket Step 3 Route the cable delivered with the card reader through the cable hole, and secure the card...
  • Page 113 IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation Figure 4-120 Securing the card reader cover Step 5 Secure the card reader mounting bracket to the post using two M4 screws, as shown in Figure 4-121.
  • Page 114: Installing An Access Controller

    IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation Figure 4-121 Installing the card reader mounting bracket ----End 4.9.3 Installing an Access Controller Context An access controller needs to be installed on an access control component mounting plate which is secured in the network cabling cabinet.
  • Page 115 IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation Figure 4-122 Unlocking an access controller Step 2 Secure the access controller to the access control component mounting plate using four M4 screws.
  • Page 116 IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation Install a floating nut into each front mounting bar.  Select an appropriate installation position in the network cabling cabinet for the access controller.
  • Page 117: Installing Switches

    IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation Figure 4-125 Securing an access control component mounting plate ----End 4.9.4 Installing Switches Context Switches can be classified into common door switches, emergency door switches, and lighting switches.
  • Page 118 IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation Figure 4-126 Removing the panel Step 2 Remove the baffle from the panel. Figure 4-127 Removing the baffle from the panel Step 3 Remove a door switch.
  • Page 119 IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation Figure 4-128 Removing a door switch (1) Switch body (2) Front cover Step 4 Secure the switch body to the switch base using M4 pan head screws.
  • Page 120 IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation Insert screws into any two diagonal holes out of the four holes on the switch body, and tighten the screws. Step 5 Clamp the switch cover to the switch body.
  • Page 121: Optional) Installing Aisle Lights

    IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation 4.10 (Optional) Installing Aisle Lights Prerequisites The customer requires aisle lights to be installed. Context Aisle lights should be installed in parallel. The first and last LED lights on aisle sides should be connected in series.
  • Page 122 IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation Figure 4-133 Interconnecting LED light tubes Procedure Step 1 Secure LED light holders to the top of the skylight connective plate using M3 screws, as...
  • Page 123: Installing Monitoring Devices

    IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation Step 2 Install an LED light onto the holders, as shown by (2) in Figure 4-134. Step 3 Use the same method to install the other LED lights, and connect the first and last lights in the...
  • Page 124 IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation Figure 4-136 Device layout in the network cabling cabinet  Install the cable rack on the rear cabinet door at the same height as the installation positions of the ECC and LAN switch.
  • Page 125: Installing The Server

    IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation Figure 4-137 Installing a floating nut 4.11.2 Installing the Server Procedure Step 1 Determine the server mounting holes in the network cabling cabinet according to the engineering drawing.
  • Page 126 IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation Figure 4-139 Installing the server Step 4 Align the two mounting ears of the server with the square hole mounting bar of the cabinet...
  • Page 127: Installing A Lan Switch

    IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation Figure 4-141 Connecting power cables for the server ----End 4.11.3 Installing a LAN Switch Procedure Step 1 Determine the LAN switch mounting holes in the network cabling cabinet according to the engineering drawing, and install floating nuts.
  • Page 128 IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation Figure 4-142 Installing LAN switches Step 3 Install a power cable between the LAN switch and the power distribution unit. The positions of power cable ports vary depending on the LAN switch models. Connect the power cable based on the actual power port of the LAN switch.
  • Page 129: Installing An Ecc Collector

    IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation 4.11.4 Installing an ECC Collector Procedure Step 1 Determine the ECC collector mounting holes in the network cabling cabinet according to the engineering drawing, and install floating nuts.
  • Page 130: Installing A Skylight Controller

    IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation Figure 4-145 Placing the VCN500 Step 3 Tighten the captive screws in the ears using a Phillips screwdriver to close the mounting ear...
  • Page 131: Installing The Lighting Control Box

    IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation Step 2 Rotate the mounting ears of the skylight controller by 180 degrees to the position shown in Figure 4-147. Step 3 Gently put the skylight controller into the network cabling cabinet, as shown by (1) in Figure 4-147.
  • Page 132: Optional) Installing An Independent Ai/Di Module

    IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation Connect a device which requires a single power supply to the 10 A output socket of the STS switch. Figure 4-148 shows the input and output ports of the STS switch. Connect the two power input ports of the STS to the PDU2000.
  • Page 133 IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation Figure 4-150 Control skylight (1) Infrared sensor mounting (2) Smoke sensor mounting (3) Rubber plugs hole hole (4) Control skylight panel (5) Reserved...
  • Page 134: Installing A Camera

    IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation 4.11.10.1 Installing a Camera Prerequisites  A camera and tools for installing it have been prepared.  A network cable for connecting the camera to the LAN switch has been prepared.
  • Page 135 IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation Figure 4-152 Installing an SD card Step 2 Connect one end of the network cable from the Ethernet port in the camera and route the other end out of the camera.
  • Page 136 IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation Figure 4-154 Triple-axis adjustment Step 4 Adjust the monitoring image, as shown in Figure 4-155. Determine an appropriate installation angle and enable manual iris control.
  • Page 137: Installing A Smoke Sensor

    IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation Figure 4-156 Installing the inner cover Step 6 Install the front cover for the camera in the direction shown in Figure 4-157 and tighten the screws on the front cover.
  • Page 138: Installing An Infrared Sensor

    IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation Context  The screws for installing a smoke sensor are located in the fittings bag of the supporting object. For example, the screws for installing a smoke sensor on the control skylight are located in the fittings bag of the control skylight.
  • Page 139: Installing Temperature Sensors

    IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation Figure 4-159 Installing an infrared sensor Step 2 Align the mounting holes in the infrared sensor with holes in the infrared sensor base, and...
  • Page 140: Installing The Audible And Visual Alarm

    IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation  The temperature sensor needs to be secured on the cable behind it 20 mm away from the sensor probe.  The temperature sensor must not be in touch with metal parts or cabinets.
  • Page 141: Installing A Wlds900 Water Detector

    IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation Procedure Step 1 Put the cable of the audible and visual alarm through the cable hole on the end door upper frame installation kit (as shown by (1) in...
  • Page 142 IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation Figure 4-162 Water detector components (1) Water detector (2) Conversion cable end A, (3) Conversion connected to the water detector cable (4) Conversion cable end B,...
  • Page 143 IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation the water detection cable to the conversion cable The water detection cable and conversion cable are interconnected through the male and female connectors.
  • Page 144: Cable Routing

    IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation When laying out the water detection cable, ensure that the water detector is close to the network cabling cabinet to facilitate further cable connections.
  • Page 145 IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation Figure 4-167 Neatly organizing cables Keep a large number of cables neat and appealing in a network cabling cabinet by using cable organizers. Locate the excess parts of cables in an unnoticeable position, as shown Figure 4-168.
  • Page 146 IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation Figure 4-169 Binding cables in different colors Cable Spacing Requirements Comply with the following requirements if possible to lay out different types of cables: Separate AC power cables to the UPS from signal cables and DC power cables.
  • Page 147 IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation Before installing a semi-flexible cable, use a dedicated tool to shape the cable. Do not shape the cable while holding the cable connector by hand.
  • Page 148 IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation Figure 4-172 Cutting off the excess part of a cable tie To prevent wire rupture due to strong stress in cables, do not bind cables with a cable tie...
  • Page 149: Cable Routing For The Dual-Row Aisle Containment Scenario

    IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation Figure 4-174 Direction for securing cable ties 4.12.2 Cable Routing for the Dual-row Aisle Containment Scenario Figure 4-175 shows how power cables and signal cables are routed in the dual-row aisle containment scenario.
  • Page 150: Routing Cables For The Network Cabling Cabinet

    IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation Figure 4-175 Routing power cables and network cables (1) Optic fiber (2) Network cable (signal cable) (3) Power cable 4.12.3 Routing Cables for the Network Cabling Cabinet Figure 4-176 shows the cable routes inside the network cabling cabinet.
  • Page 151: Installation Positions For Monitoring Components

    IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation Figure 4-176 Routing cables for the network cabling cabinet (1) Power cable (2) Signal cable 4.12.4 Installation Positions for Monitoring Components Figure 4-177 shows the installation positions of monitoring components.
  • Page 152: Cable Routing For The Door Monitoring Components

    IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation Figure 4-177 Component installation positions (1) Door exit button (2) Lighting switch (3) Emergency door release button (4) Card reader (5) Audible and visual alarm...
  • Page 153: Cable Routing For The Sensors On The Control Skylight

    IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation Figure 4-178 Cable routing for monitoring components Notes for cable route:  Both the card reader and door open switch connect to the access controller in the network cabling cabinet.
  • Page 154: Cable Routing For The Aisle Lighting System

    IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation Figure 4-179 Cable route for sensors Notes for cable route A:  The camera connects to the LAN switch in the network cabling cabinet.
  • Page 155 IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation Figure 4-180 Cable routes for the aisle lighting system (A) Connecting to the lighting controller cabinet in the network cabling cabinet After connecting aisle lights in series, connect the unused end of the outermost light to its delivered cable.
  • Page 156: Cable Routes For Skylight Magnetic Locks

    IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation Figure 4-181 Cutting off the plug of the LED light Figure 4-182 Pressurizing cables using a multi-wire terminal The cable outlets of aisle lights are on the skylight connecting plates. See the magnified view in Figure 4-180.
  • Page 157: Connecting Module Ground Cables

    IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation Figure 4-183 Cable routes for skylight magnetic locks (A) Connecting to the skylight controller in the network cabling cabinet 4.12.9 Connecting Module Ground Cables The grounding system of a data center must be a TN-S or TN-C-S system.
  • Page 158 IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation Figure 4-184 Base grounding diagram (1) Base ground points  Connect one end of the base ground cable to any of the base ground points shown by (1) Figure 4-184, and connect the other end to the ground busbar of the equipment room.
  • Page 159 IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation  If cabinet ground bars are deployed, connect ground cables from servers to the ground bars, and connect the ground bars between cabinets in sequence, which are then connected to the ground bar in the PDU8000.
  • Page 160: Cable Installation For The Power Supply And Distribution System

    IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation Figure 4-187 Grounding a dual-row aisle containment 4.12.10 Cable Installation for the Power Supply and Distribution System 4.12.10.1 Connecting Battery Cables Precautions for Connecting Battery Cables ...
  • Page 161 IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation Connecting Battery Cables  When the length of a battery cable equals the distance between two battery terminals, connect the cable straight through, as shown in Figure 4-188.
  • Page 162 IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation Figure 4-190 Incorrect battery cable connection method Connecting Cables to a Busbar When configuring two battery cabinets, install a copper busbar in one of the cabinets. Connect the circuit breakers to the busbar after the circuit breakers are connected to the batteries.
  • Page 163 IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation Introduction to Battery Cabinets and Batteries The micro-module data center supports multiple battery configurations. Figure 4-192 is a picture when batteries are installed inside a battery cabinet.
  • Page 164 IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation Component Configuration Qty. Battery 100 Ah battery with charge One string with 32 batteries voltage of 384 V Battery tray Battery tray for 4 batteries...
  • Page 165: Cable Connections For Power Supply And Distribution Devices

    4.12.11 Connecting Cables for the Temperature Control System The IDS2000 temperature control system includes only a NetCol5000-A020 air-cooled in-row precision air conditioner. For details about the cable connection methods, see the user manual delivered with the product.
  • Page 166 IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation Figure 4-194 Preparing a cord end terminal Preparing an RS485 Monitoring Cable Figure 4-195 shows how to prepare a cord end terminal for the ECC collector.
  • Page 167: Connecting The Server Monitoring Cable

    IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation 4.12.12.2 Connecting the Server Monitoring Cable Prerequisites A network cable used for monitoring is prepared. Procedure Step 1 Connect one end of the network cable to the gigabit Ethernet port 1 on the server.
  • Page 168 IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation Context Bind the SMS modem to the rack mounting bar at the rear of the network cabling cabinet near the server using cable ties.
  • Page 169: Connecting The Lan Switch Monitoring Cable

    IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation Table 4-12 Relations between the status of the indicator and the SMS modem Indicator Modem The SMS modem is activated and is not registered with the network.
  • Page 170: Connecting A Monitoring Cable To The Ecc Collector

    IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation 4.12.12.5 Connecting a Monitoring Cable to the ECC Collector Procedure Step 1 Connect cables to the ECC collector, as shown in Figure 4-199 Table 4-14.
  • Page 171: Connecting A Monitoring Cable To A Lighting Control Box

    IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation Procedure Step 1 Connect one end of the network cable to the GE1 or GE2 port on the VCN500, as shown in Figure 4-200.
  • Page 172 IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation Figure 4-201 Connecting the power cable to the lighting control box (1) Cable 04050188 (2) Terminal 14170203 (3) Cable 25030384 (4) PDU8000 circuit breaker Connect one end of cable 04050188 to the power port on the lighting control box.
  • Page 173: Connecting A Monitoring Cable To The Skylight Controller

    IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation Port Function INFARA4 (pole insensitive). INFRA POWER Connects to the power cable for the infrared sensor switch (pole sensitive), with the brown wire connecting to pole L and blue wire to pole N.
  • Page 174 IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation Figure 4-203 Cable connections for the skylight controller Table 4-16 shows how to connect cables. Table 4-16 Cable connections to the ports of the skylight controller...
  • Page 175: Connecting An Access Controller Monitoring Cable

    IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation Port Connection Method cascading mode (in a customized scenario), this port connects to the LINK OUT port of the next skylight controller.
  • Page 176 IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation Figure 4-204 Cable connections of door exit buttons and access card readers Figure 4-205 shows the cable connections to the electromagnetic double-swing door lock and an emergency door release button (a break glass switch is configured optionally).
  • Page 177 IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation (5) Four-core cable B (6) Back of the emergency door release button Secure terminal block A near the magnetic locks using cable ties.
  • Page 178: Connecting A Monitoring Cable To A Camera

    IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation (3) Four-core cable A (4) Terminal block B (5) Four-core cable B (6) Back of the emergency door release button (A) To the access controller in the network cabling cabinet 4.12.12.10 Connecting a Monitoring Cable to a Camera...
  • Page 179: Connecting A Monitoring Cable To A Smoke Sensor

    IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation Figure 4-207 Connecting a monitoring cable to a door status sensor Step 2 Assemble the door status sensor by performing steps in Step 1 in the reverse order.
  • Page 180: Connecting A Cable To The Wlds900 Water Detector

    IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation 4.12.12.13 Connecting a Cable to the WLDS900 Water Detector Prerequisites  A monitoring cable required has been prepared.  You are familiar with the functions of all ports on the ECC collector by referring to Introduction to ECC Ports.
  • Page 181: Connecting A Monitoring Cable To The Ms899 Electronic Lock

    IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation Each AI/DI module can be connected to a maximum of eight temperature sensors. Step 3 Connect the AI/DI module to the COM/DC 12V port on the ECC500 using a network cable to provide RS485 communication and power supply.
  • Page 182: Connecting The Netcol5000-A020 Monitoring Cable

    IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation Figure 4-209 PDU2000 wiring ports Connect the other end of the network cable to the COM port on the ECC collector. Step 2 (Optional) Connect a PDU2000 cascading cable. Use a common network cable to connect port COM1 or COM2 on the PDU2000 to the port COM1 or COM2 of another PDU2000.
  • Page 183 IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation Figure 4-210 NetCol5000-A020 communications port (1) Teamwork communications port 1 (2) Teamwork communications port 2 Step 2 Open the NetCol5000-A020 electric control box and verify the DIP switch settings.
  • Page 184: Connecting Pdu8000 Monitoring Cables

    IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation  In the non-teamwork networking scenario, connect one communications port of the device to the COM port on the ECC collector. ...
  • Page 185: Optional) Installing Base Decorative Plates

    IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation Figure 4-213 Connecting PDU8000 monitoring cables Step 2 Connecting the ATS monitoring cable: Prepare a cord end terminal on one end of the RS485...
  • Page 186: Installing Cabinet Sealing Plates

    IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation Figure 4-214 Installing a decorative plate for a base ----End 4.14 Installing Cabinet Sealing Plates Context Cabinet sealing plates are used to seal cabinets and their bottoms to ensure that an aisle is airtight.
  • Page 187 IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 4 Hardware Installation Figure 4-215 Installing cabinet sealing plates ----End Issue Draft A (2015-06-29) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
  • Page 188: Checking The Installation

    IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 5 Checking the Installation Checking the Installation B Checking the Installation lists the items to be checked. Issue Draft A (2015-06-29) Huawei Proprietary and Confidential...
  • Page 189: Power-On Commissioning

    IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 6 Power-On Commissioning Power-On Commissioning After the installation is completed, power it on and commission it to check that all components are intact after transportation and installation, and that the components can run continuously, reliably, and stably.
  • Page 190: Commissioning The Power Supply And Distribution System

    IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 6 Power-On Commissioning Figure 6-1 Power-on Commissioning Process 6.2 Commissioning the Power Supply and Distribution System For details about how to commission each device in the power supply and distribution system, see the documents delivered with it.
  • Page 191: Configuring The Facility Management System

     The NetCol5000-A PID value can be adjusted only by a Huawei engineer. To commission a temperature control device, follow instructions in the documents delivered with it.
  • Page 192 IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) 6 Power-On Commissioning Category Device name LAN switch Access control system Door status sensor VCN500 Camera Smoke sensor Skylight controller Audible and visual alarm Water sensor...
  • Page 193: A Appendix

    IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) A Appendix Appendix A.1 (Optional) Connecting Linkage Cables Between the Gas Extinguishing Controller and ATS Context After linkage cables are connected between the gas extinguishing controller and ATS, if the gas extinguishing controller generates a fire signal, the ATS disconnects non-firefighting power supply and stops supplying power to precision air conditioners in the data center.
  • Page 194 IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) A Appendix Figure A-1 Connecting linkage cables between the fire alarm bell and ATS  Connect linkage cables between the drive output ports for the audible and visual alarm...
  • Page 195: Optional) Connecting The Linkage Cables Between The Fire Extinguishing System And Access Controller

    IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) A Appendix A.2 (Optional) Connecting the Linkage Cables Between the Fire Extinguishing System and Access Controller After linkage cables are connected between the fire extinguishing system and access controller, the access controller opens data center doors when the fire extinguishing system generates an alarm signal.
  • Page 196: Introduction To Ecc Ports

    IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) A Appendix A.3 Introduction to ECC Ports Before connecting cables, get familiar with the ports on the ECC collector. For details about port positions and the ECC collector appearance, see ECC500 V600R001C00 User Manual.
  • Page 197 IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) A Appendix Port Description electronic door locks.  1: A  2: B  3: 12 V DC  4: A  5: B ...
  • Page 198: Ports On The Skylight Controller

    IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) A Appendix  Sensors including 4 mA to 20 mA sensors, door status sensors, water sensors, and smoke detector provide data for the ports. ...
  • Page 199 IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) A Appendix Port Function Remarks visual alarm. alarm generates an alarm when the system is faulty. Configuration on the NetEco is not required. 1 (+ -) –14 (+ -)
  • Page 200 IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) A Appendix Position Function Scenario Example The toggle switches are both For a skylight lock with a bolt, the 1 (+ –) to 14 (+ –) NO by default.
  • Page 201: B Checking The Installation

    IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) B Checking the Installation Checking the Installation Cabinet Installation Check Table B-1 Cabinet installation checklist Check Item Expected Result □ Compliant □ The cabinet layout position is consistent with the equipment room layout diagram.
  • Page 202 IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) B Checking the Installation Check Item Expected Result Incompliant especially the cable joints between network cables and in the cabinet. □ Compliant □ Check that exposed parts near the wiring terminals and...
  • Page 203 IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) B Checking the Installation Check Item Expected Result □ Compliant □ Check that batteries are neat and does not leak electrolyte. Incompliant □ Compliant □...
  • Page 204: C Acronyms And Abbreviations

    IDS2000 Intelligent Micro-Modular Data Center Installation Guide (2000 mm High Cabinet in Dual-Row Aisle Containment) C Acronyms and Abbreviations Acronyms and Abbreviations Automatic Transfer Switch Energy Control Center Integrated Data Center Solution Internet Technology Light Emitting Diode Polyvinyl Chloride Uninterruptible Power System...

Table of Contents