UPS5000-E-(50 kVA-125 kVA) User Manual (Integrated UPS 3.0) Issue Date 2019-12-20 HUAWEI TECHNOLOGIES CO., LTD.
Page 2
Notice The purchased products, services and features are stipulated by the contract made between Huawei and the customer. All or part of the products, services and features described in this document may not be within the purchase scope or the usage scope. Unless otherwise specified in the contract, all statements, information, and recommendations in this document are provided "AS IS"...
The "NOTICE", "WARNING", and "DANGER" statements in this document do not cover all the safety instructions. They are only supplements to the safety instructions. Huawei will not be liable for any consequence caused by the violation of general safety requirements or design, production, and usage safety standards.
Do not power on the equipment before it is installed or confirmed by professionals. 1.2 Personnel Requirements Personnel who plan to install or maintain Huawei equipment must receive thorough training, understand all necessary safety precautions, and be able to correctly perform all operations.
Metal shavings from drilling may short-circuit boards inside the equipment. Obtain the consent from the customer, subcontractor, and Huawei before drilling. Wear goggles and protective gloves when drilling holes. ...
Page 21
The site must be equipped with qualified fire extinguishing facilities, such as firefighting sands and powder fire extinguishers. To ensure battery safety and battery management accuracy, use batteries provided with the UPS by Huawei. Huawei is not responsible for any battery faults caused by batteries not provided by Huawei. Battery Installation Before installing batteries, observe the following safety precautions: ...
Check that the fittings comply with the packing list. If some fittings are missing or do not comply with the packing list, record the information and contact your local Huawei office immediately. If the UPS installation environment is in poor condition and the UPS will be stored for a long time after it is unpacked, wrap the UPS with the original plastic coat to prevent dust.
3.2.6 Connecting Signal Cables 3.2.6.1 Connecting a Remote EPO Switch Huawei does not provide an EPO switch and cable. Prepare them before installation. The 22 AWG cable is recommended. AWG is short for American wire gauge. To prevent problems, equip the EPO switch with a protective cover, and enclose the cable with a protective tube.
Context Perform system commissioning and power-on strictly according to the system manual and ATS instructions. For any changes in operations and parameters, consult Huawei engineers. Otherwise, system commissioning or power-on may fail, or even the cabinet is damaged. Issue 09 (2019-12-20)
Step 1 (Skip this step in the case of ATS input.) Turn on the MCCB. Step 2 Turn on the UPS input circuit breaker QF1. The UPS is powered by the mains and initialization begins. The LCD displays the Huawei logo and an initialization progress bar.
Page 175
User Manual (Integrated UPS 3.0) 5 Operations The Service Expert app can be downloaded from Huawei app store and can run on Android. User interfaces displayed in this document correspond to the app version V100R001C00B055 and are for reference only.
Step 4 Press and hold down the BATT start button on the bypass module for at least 2 seconds. The system automatically enters the battery cold start status. The LCD displays the Huawei logo and an initialization progress bar.
EOD voltage and 11.3 V/cell. 2. Restore the mains power supply to start the inverter. Close the battery switch and charge batteries until each battery has a voltage greater than the EOD voltage and 11.3 V/cell. If any unmentioned faults occur, see the alarm list chapter, or contact Huawei technical support. Table 7-1 Troubleshooting...