Q U I C K S TA R T G U I D E
Zenith ZTG series
Enclosed ATS, 30-1200 A, 200-480 Vac
This document is not intended to replace document 1SCC303023M0201, ZTG series O&M, which is called
out in some cases for further detail. This quick start guide is intended to help the user power the ATS
and make it fully operational with a few simple steps. This document references the manual frequently
for further details.

Advertisement

loading

Summary of Contents for ABB Zenith ZTG Series

  • Page 1 — Q U I C K S TA R T G U I D E Zenith ZTG series Enclosed ATS, 30-1200 A, 200-480 Vac — This document is not intended to replace document 1SCC303023M0201, ZTG series O&M, which is called out in some cases for further detail.
  • Page 2 — About your ZTG series ATS Zenith ZTG(D) series construction Zenith ZTG(D) series ATS consists primarily of the TruONE™ power panel and an electrical enclosure. The TruONE Level 3 power panel integrates switch, mechanism, controller, power supply, HMI, and all connectivity accessories into one seamless unit.
  • Page 3 ATS, even without any line voltage or auxiliary power connected to the panel. This USB module plugs directly to the HMI. Download the Ekip Connect https://library.abb.com/en/ software and manual from the QR code or the web address at the right.
  • Page 4: Auxiliary Contacts

    — Auxiliary contacts Auxiliary contacts will be shipped loose. Use Table 1 and Figure 3 to apply A (NO) and B (NC) contacts for correct operation. Each source has two separate mounting points capable of holding up to two aux contacts each for position indication, for a total of four per source.
  • Page 5 — Energizing For detailed instructions on installing your enclosed ATS and installing accessories, see sections 9 and 10 of the ZTG(D) O&M manual. Before energizing the panel: 1. Confirm that installation has been performed by a qualified person and in accordance with NFPA 70 (NEC).
  • Page 6 — HMI keypad operation Auto Alarm reset Figure 4 1. Esc: Step back in menu. Displays alarms when pressed from home screen. 2. Up, Down: Move in menu screens. 3. Enter: Opens menu from home screen. Select next screen,and set orconfirm value or function.
  • Page 7: Auto Configure

    — Auto Configure Auto configure is the first step to take after the panel is initially energized. This function recognizes the electrical system, then automatically sets all the system parameters: system voltage, frequency, and phase sequence. Follow the steps in the figure on the HMI to run auto configure. The ATS must have at least one source available to complete this step.
  • Page 8 — Settings (Optional) Time delays Default Value Possible range Override momentary outage (separate for S1 and S2) 2 s 0-60 s Transfer from S1 to S2 (separate for S2 to S1) 0-3600 s Center-off delay 0-300 s Generator stop 0-60 min Set points Voltage and frequency drop-out ±15% of nominal...
  • Page 9 — Settings (Optional) If the standard I/O or any com modules such as Ekip 2k Signaling I/O must be programmed, these can be set in the same manner, by following the appropriate path below from the main menu. Settings>Standard I/O Settings or Settings>Modules Figure 6...
  • Page 10 — Confirm Automatic Operation To put your ATS into Auto mode, confirm the slide switch is in “AUTO” before the enclosure door is closed. This slide switch overrides the Auto/Manual mode set from the HMI. To place ATS controller in auto mode, press the auto key on the HMI as in Figure 7.
  • Page 11 — Test Run an off-load test to verify the ATS-generator control connection. Follow steps in Figure 8. Backup source (generator) should start and be indicated by solid green LED for secondary source. Repeating this sequence will turn off generator. Figure 8 To test ATS-generator auto operation, while in auto mode, simulate a primary source failure by opening the circuit breaker immediately upstream to the ATS's primary source.
  • Page 12 +1 (800) 637-1738 epis.pqservice@abb.com http://solutions.abb/zenith — Manual and automatic operation - TruONE ATS Video https://www.youtube.com/watch?v=bosvSPVi2sM Installation of accessories - TruONE ATS Video https://www.youtube.com/watch?v=qV2KoIv38GY User O&M manual ZTG © Copyright 2019 ABB. All rights reserved. Specifications subject to change without notice.