Installation - Siemens SINAMICS S120 Equipment Manual

Chassis liquid cooled power units
Hide thumbs Also See for SINAMICS S120:
Table of Contents

Advertisement

3.5

Installation

Figure 3-6
Crane lifting lugs
Power Modules are fitted with crane lifting lugs as standard when shipped. The units can be
hoisted from these lugs and transported from the pallet to the installation location.
Note
A thread for inserting a crane lifting lug is provided on the bottom of the Power Module. This
allows the Power Module to also be transported horizontally with a lifting harness.
A lifting harness with vertical ropes or chains must be used to prevent any risk of damage
to the housing.
The crane lifting lugs must be removed after the modules have been installed. The lugs
should be safely stored for future use.
Chassis Liquid Cooled Power Units
Manual, (GH7), 01/2011, 6SL3097-4AM00-0BP1
Crane lifting lugs / screw coupling points for mechanical support
WARNING
Power Modules
3.5 Installation