Ac Input Commissioning - Samsung 136S Installation Manual

Lithium ion battery system for ups
Hide thumbs Also See for 136S:
Table of Contents

Advertisement

 Screw fastening torque by sampling
 High-voltage cable connection
 Module connections
 Switchgear connections

3.9.10 AC Input Commissioning

When the installation and assembly of the battery system is complete, notify the system supplier for
system commissioning. Special tools and training are required for commissioning.
CAUTION
Do not energize the input or control power prior to commissioning.
ET003222373
English 4/2018. Rev 0.0
.
Assembling the Product