CHAPTER 2: INSTALLATION
Zero-Sequence CT Installation
845 TRANSFORMER PROTECTION SYSTEM – INSTRUCTION MANUAL
The figure below shows the various CT connections and the exact placement of a Zero
Sequence current CT, so that ground fault current can be detected. Twisted pair cabling on
the Zero Sequence CT is recommended.
Figure 2-26: Zero Sequence (Core Balance) CT Installation
UNSHIELDED CABLE
Source
A
B
C
N
LOAD
Ground connection to neutral
must be on the source side
G
Ground
outside CT
ELECTRICAL INSTALLATION
SHIELDED CABLE
Stress cone
Source
shields
A
B
C
To ground;
LOAD
must be on
load side
996630A5
2–23