56
Fix the pedestal to the drive frame in reverse order to step Remove the pedestal:
1. Fix the fastening screws.
2. Connect the terminals at the top of the pedestal to the terminals at the bottom of the upper part of
the drive frame.
3. Tighten the connections.
Fasten the drive frame to the wall (recommended):
Fasten unit with screws or bolts to the holes in the wall.
Note: In mounting orientation a, do not fasten the unit to wall if it is subjected to sideways vibration.
Connect the control cables as described in section
Fasten the covers

Mounting orientation c (lifting from above)

Make the installation otherwise as described in
leave the pedestal connected to the frame.
• Remove the lead-through plate and the lower front and side plates.
• Lift the drive frame onto the lead-through plate from above.
• Fasten the drive to the floor.
• Connect the cable lugs to the terminals.
• Fasten the lower front and side plates.
• Fasten the drive by top to the wall (recommened).
Note: When mounting the unit on wall, a support shelf is required, see the
instructions in ACS800-02/U2 Application Note on Wall Mounting [68250013
(English)].
Installation
WARNING! The fixing is important because the screws are required for the grounding of the
drive.
WARNING! Be careful not to drop screws inside the pedestal. Loose metal pieces inside the
unit may cause damage.
View of frame size R7
1
2
1
Terminal connection screws
R7: M8 combi screws
Tightening torque: 15...22 Nm (0.59...0.87 lbf ft)
R8: M10 combi screws
Tightening torque: 30...44 Nm (22...32 lbf ft)
Connecting the control
Mounting orientations a and b
cables.
but