4.2.3. Metal frame foundation

1.
Place the frame (A) in the desired position and mark the position of the holes for drilling.
The hole distance of 655mm on either side of the metal frame foundation
is not equal to the hole distance (680 mm) from the HVC 150(S) cabinet.
See also the mechanical drawing in Appendix D Dimensions of the Power
Cabinet's Metal Foundation.
2.
Remove the frame.
3.
Drill and tap holes at the marked positions. The holes must be suitable for bolt size M16.
4.
Route the cables tray through one of the cable openings (B).
5.
Align the frame (A) with the tapped holes.
6.
Insert the bolts (C) fitted with the washers (D) into the holes (4x).
7.
Tighten the bolts.
8.
Route the AC power cable through the left cable opening (B). Make sure that a cable
length of 1000 mm is available above the floor for internal routing in the cabinet.
This extra cable length is required to connect the AC power cable with
the connectors in the Power Cabinet without problems.
Document: v0.4 / Document No.: TBA | Date: 11-08-2021
HVC-R 100/150 E-Bus Charger Installation Guide
NOTICE
NOTICE
Page 41 of 131

Advertisement

Table of Contents
loading

This manual is also suitable for:

Hvc-r 150

Table of Contents