Operation

6
Operation
6.1

Prepare before use

Preliminary requirements
Procedure
1. Make sure that the EVSE is installed according to the instructions in this manual.
2. Make an emergency plan that instructs people what to do in case of an
emergency.
3. Give these instructions to each end user:
4. The commissions the EVSE must be done by the manufacturer or a
trained technician. Contact the manufacturer when the EVSE is ready for
commissioning. Refer to section 1.12.
5. Make sure that the space around the EVSE cannot get blocked. Think of snow or
other objects. Refer to the floor space requirements. Refer to section 10.12.5.
6. Make sure that maintenance is done on the EVSE. Refer to section 7.1.
7. If the EVSE is de-energized for more than two hours, activate the internal heater
to remove condensation from the cabinet. Refer to section 6.7.
6.2

Stop the EVSE if there is an emergency

Preliminary requirements
Procedure
1. If there is an emergency, push the
58
Owner
Emergency stop. Refer to section 6.2.
Charge session. Refer to section 6.4.
Danger:
General risk
Make sure that you have approval of a trained technician,
from the manufacturer or a third party, to use the EVSE after
commissioning. After approval, do not move the EVSE.
Caution:
Remove condensation before use, to prevent damage to the EVSE.
Owner
The EVSE stops all charge sessions.
The touchscreen shows a message.
emergency stop button.