2.3.
Installing a Hitachi DS7080 Server
D048
D048:
The server weighs 160 kg when fully populated.
Important The server is delivered fully populated. It is mandatory to
See
Required screws, nuts and washers
See
Required tools
T25 Torx screwdriver
Flat screwdriver
Lifting device
Procedure
1. Prepare the rails
1. Loosen the four screws of each rail.
2-14
Installation Guide
DANGER
use a lifting device to install it.
However, it is possible to reduce the server weight by
removing the components from the compute box.
Appendix Installing a Lightened Server, on page A-1