5.2.1 Determining the Pre-fab. Module Installation Position

Prerequisites
Concrete platform levelness is critical to pre-fab. module installation. Ensure that
the concrete platform meet requirements before installing pre-fab. module bases.
Context
Before installing pre-fab. modules, determine their installation positions and
directions based on site space.
Figure 5-6 Single-capacity base (unit: mm)
Preparations
Tools: torque wrench, adjustable wrench, level, level gauge, hammer drill, right
angle, marker, ink fountain, long leather measuring tape, claw hammer, vacuum
cleaner
Materials: single-capacity base, twistlock, expansion bolt, spacer
Skill requirement: skilled technician
Procedure
Step 1 Determine the installation areas on the concrete platforms, and the actual site
space. Mark the installation areas on the concrete platforms using an ink fountain.
Step 2 Determine the installation position for the first base in the installation area based
on the site space, and draw longitude and latitude reference lines between the
first base and other bases.
Issue 07 (2022-12-15)
The field meets site requirements.
Before installing pre-fab. modules, check the height of concrete platforms and
ensure that the height (altitude) error between the upper surfaces of all
platforms does not exceed 5 mm.