Cables must be bound neatly, and cable ties must be secured evenly and properly
in the same direction.
----End
A.1.6 Routing Cables into Feeder Windows
DPJ end connectors and waterproof metal connectors are available on pre-fab.
module feeder windows. When routing cables through a feeder window, follow the
appropriate installation procedure.
● After cables are routed into feeder windows on the ends of pre-fab. modules,
use Styrofoam to seal the hole inside the pre-fab. modules.
● The armored cables must be grounded.
External cables must be routed from bottom to top and have backwater bend.
Figure A-4 Backwater bend
A.1.6.1 Installing DPJ End Connectors
Prerequisites
Except armored power cables, other external cables of the FusionModule1000 must be routed
through a feeder window using DPJ end connectors.
Context
A DPJ end connector consists of a body, ferrule, guarding, and cover lock nut, as
shown in
Issue 07 (2022-12-15)
NO TICE
NO TICE
Do not operate a feeder window outdoors under bad weather conditions if no
shelter is available.
Cables have been mounted on cable trays.
Cables need to be routed into a feeder window using DPJ end connectors.
NO TE
Figure
A-5.