NetCol5000-C(030, 032, 065) In-row Chilled Water
Smart Cooling Product
User Manual
Step 2 Tap Yes. The checking before startup screen is displayed, as shown in
Figure 5-17 Checking before startup
Step 3 Tap Yes for check items one by one according to the prompt messages on the
screen.
Step 4 Tap Yes and enter the screen where you select commissioning items, as shown in
Figure
Figure 5-18 Selecting commissioning items
Step 5 Tap Yes. The component startup commissioning screen is displayed, as shown in
Figure
Issue 06 (2022-12-15)
NO TE
● For the initial startup wizard, Last record is in grey, indicating that the operation is not
allowed.
● For the non-initial startup wizard, choose Last record and you can view the last startup
wizard report.
5-18.
NO TE
● If the system is not configured with the humidifier components, the humidifier
commissioning items will not appear on the screen.
● If the humidification function is disabled, the humidifier commissioning item cannot be
selected.
● All the items are selected by default if you first enter the screen where you select
commissioning items. Except that the indoor fan item is mandatory, you can clear other
commissioning items that are not required.
5-19.
Copyright © Huawei Digital Power Technologies Co., Ltd.
5 Power-On Commissioning
Figure
5-17.
124