18. Once the server is located in its designated position, using an adjustable
wrench, lower the leveling pads to secure the server in place.
See Figure 9A.
Figure 9. Lowering the Leveling Pads
20. At the front of the system, remove the single screw securing the front
stabilizer and pull the stabilizer out from the cabinet as shown in Figure 10.
Figure 10. Releasing the Front Stabilizer
A
Leveling Pad
Express5800/1080Xd Installation Procedures 11