LUNA2000-200KTL-H0 Smart Power Control System
User Manual
4.7 Installing the Smart PCS on the DCBOX
Installation Description
●
●
Installation Diagram
Figure 4-16 Installation
Issue 05 (2022-06-30)
NO TE
● A maximum of five Smart PCSs can be installed on the top of the DC LV Panel (DCBOX).
If less than five Smart PCSs will be installed, install them from left to right. Otherwise,
the Smart PCS fasteners cannot be used.
● The installation method of all Smart PCSs is the same. Install the Smart PCS according
to the direction shown in the figure. This section uses one Smart PCS as an example.
Use the DCBOX-9/5-H0 DCBOX purchased from the Company.
DCBOX DC LV Panel User Manual .
For details, see
Copyright © Huawei Technologies Co., Ltd.