Huawei LUNA2000-100KTL-M1 User Manual page 37

Smart power control system
Hide thumbs Also See for LUNA2000-100KTL-M1:
Table of Contents

Advertisement

LUNA2000-100KTL-M1 Smart Power Control System
User Manual
● Four persons or appropriate transportation tools are required to move the
● Place a foam pad or cardboard under the device to protect its enclosure from
● Use lifting handles to facilitate installation, which are optional and delivered
● Secure the lifting handles (with the steel washers of the lifting handles closely
● If the stud of a lifting handle is bent, replace the lifting handle in time.
● Slowly and steadily hoist, land, and move the Smart PCS to avoid bumping and
Methods for Moving the Smart PCS
If the installation position is high and a crane is required, run a sling (strong
enough to bear the weight of the Smart PCS) through the two lifting eyes to hoist
the Smart PCS.
Table 4-1 Method description
Method
Manual
handling
Hoisting
Note [1]: The hoisting capability of the crane shall be greater than or equal to 2
t, the working radius shall be greater than or equal to 2 m, and the length of
the lifting sling shall be greater than or equal to 1.8 m. To prevent damage to
the device surfaces, you are advised not to use metal slings such as steel wire
ropes.
Hole Description
Issue 07 (2023-07-15)
NO TICE
device.
damage.
separately. Ensure that the lifting handles are securely installed. After the
installation is complete, remove the lifting handles and keep them properly.
fitted to the battery pack).
damaging the device enclosure.
Tool
Lifting handles
Crane sling
Copyright © Huawei Technologies Co., Ltd.
[1]
4 Installing the Smart PCS
Description
Prepared by the
customer
Prepared by the
customer
31

Advertisement

Table of Contents
loading

This manual is also suitable for:

Fusionsolar luna2000-100ktl-m1Fusionsolar luna2000-200kwh-2h1

Table of Contents