N68-22 Cabinet Installation Guide
Step 10 Check whether the unpacked boards need to be installed immediately, and then proceed
accordingly.
If...
The unpacked boards need to be installed
immediately
The unpacked boards need not be installed
immediately
Step 11 Check the items. Check the items one by one according to the names, types, and quantities
described in the Packing List.
The acceptance of items covers the following aspects:
l Appearance: Check whether there is any visible defect, looseness, distortion, or damage;
l Integrity: Ensure that all the parts and accessories required for the installation of cabinets are
l Computer: Check whether the monitor, keyboard, and mouse are intact and in good condition.
l Board: Ensure that the type and quantity of the boards are consistent with those in the Packing
If...
The packing list indicates "shortage of
articles"
There are any short, wrong, extra, or
damaged items
The shipment is intact
----End
Issue 01 (2013-01-30)
check whether the labels are legible and whether the nameplates and decorating plates are
available and meet the requirements.
available.
List. Ensure that no printed circuit board is broken and no component is detached from the
board.
NOTE
The project supervisor should take the major role in the inspection of equipment and components whose
electric characteristics are likely to have been affected.
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
3 Preparing for the N68E-22 Cabinet Installation
Then...
Place the boards on an ESD surface and
discharge the static electricity.
Pack the boards with the original materials and
place them in a cool dry place away from direct
sunlight or strong electromagnetic radiation.
Then...
Inform the order management engineer at the
local office. Then, sign the Packing List together
with the customer.
Representatives of Huawei and the customer
must sign the Unpacking Inspection Memo and
Packing List. The installation supervisor must fill
in the Cargo Problems Report and inform the
order management engineer at the local office in
three days. The installation supervisor must keep
the problematic items intact and the inner and
outer packing intact for future investigation and
verification.
Place the inspected items by type. Then,
representatives of Huawei and the customer sign
the Packing List.