Huawei ESS-240V12-9AhBPVBA04 Quick Manual page 28

Hide thumbs Also See for ESS-240V12-9AhBPVBA04:
Table of Contents

Advertisement

ESS-240V12-(9AhBPVBA04, 7AhBPVBA04) Battery
Pack
Quick Guide
Figure 3-18 Connecting cables to battery packs for a single UPS2000-G-15 kVA/20
kVA
Connecting Cables to Shared Battery Packs for a UPS2000-G-15 kVA/20 kVA
Parallel System
Issue 01 (2021-12-23)
NO TE
If the 15 kVA/20 kVA UPS parallel system does not share battery packs, the cable
connection methods for each UPS and battery pack in the parallel system are the same as
those in a single 15 kVA/20 kVA UPS system.
Copyright © Huawei Digital Power Technologies Co., Ltd.
3 Installation
23