The module is delivered in a two-level package. Unpack the package as shown
below.
1
2
3
Move the transport package by pallet truck to the installation site. Lift up the
top cover. The following items are located in the upper package (1):
• pedestal
• output busbars U2, V2 and W2
• supports, screws and terminals for the output busbars and PE grounding
• fastening brackets for base and wall mounting
• busbars for brake resistor connection (if brake chopper is ordered)
• adapter (if output busbars on the short side of the module)
• DC busbars (if ordered)
• control panel and a 3 m (98 in.) cable (if ordered)
• control panel mounting platform (if ordered).
In the lower package (2):
• drive module.
Below the drive module (3):
• Drive Control Unit (RDCU). Note: The fibre optic cables and power supply
cable to be connected to the RMIO board inside the RDCU unit are wound
on the top of the drive module.
• optional modules (if ordered) factory installed onto the RMIO board in the
RDCU unit
• residual voltage warning and output busbar stickers
• hardware manual
• appropriate firmware manuals and guides
• delivery documents
• optional module manuals.
Undo the fastening
screws.
Mechanical installation of non-pre-assembled units (ACS800-04M)
Top view
47