Preparation

2-4
To prepare the CTF878 for a software update:
1. Disconnect the power to the CTF878.
The main power to the CTF878 must be disconnected
2. Open the enclosure, remove the main aluminum shroud and locate
the J13 header connector (above the display connector) on the
main board (see Figure 2-3 below).
3. Remove the "CONFIG" jumper from the top two pins.
"CONFIG"
JUMPER
Figure 2-3: J13 Header Connector
4. Reinstall the shroud, close the cover, and reapply power to the
CTF878.