Page 1
ValkDouble Installation manual Van der Valk Solar Systems Solar Mounting Systems Version 03 | EN...
Page 2
Page 03 Alu profiles Page 04 Push rods Page 05 Ballast Page 06 Placing panels Page 07 Placing panels Page 08 Cable clamp Page 09 Table of contents ValkDouble Van der Valk Solar Systems Solar Mounting Systems Version 03 | EN...
Page 3
Our terms and conditions shall apply to all our products and can be found on our website: www.valksolarsystems.nl. Van der Valk Solar Systems B.V. does not accept any liability for any direct and/or indirect consequences of any act (or omission) ensuing from the information in or the failure to observe the instruction provided in the project report and the installation manual and for possible incorrect results resulting from the use of this online calculation tool which was made available to you.
Page 4
Required ballast | The Netherlands General The ValkDouble® mounting system must be reinforced by means of tiles, which must be Note 1: The extra ballast must be equally divided over the ballast foundations. placed on the indicated ballast foundations. In three steps you can easily calculate the Note 2: The max.
Page 5
Required ballast | Belgium General The ValkDouble® mounting system must be reinforced by means of tiles, which must be Note 1: The extra ballast must be equally divided over the ballast foundations. placed on the indicated ballast foundations. In three steps you can easily calculate the Note 2: The max.
Page 6
Required ballast | Germany General The ValkDouble® mounting system must be reinforced by means of tiles, which must be Note 1: The extra ballast must be equally divided over the ballast foundations. placed on the indicated ballast foundations. In three steps you can easily calculate the Note 2: The max.
Page 7
Required ballast | United Kingdom General The ValkDouble® mounting system must be reinforced by means of tiles, which must be Note 1: The extra ballast must be equally divided over the ballast foundations. placed on the indicated ballast foundations. In three steps you can easily calculate the Note 2: The max.
Page 8
Required ballast | Ireland General The ValkDouble® mounting system must be reinforced by means of tiles, which must be Note 1: The extra ballast must be equally divided over the ballast foundations. placed on the indicated ballast foundations. In three steps you can easily calculate the Note 2: The max.
Page 9
Required ballast | Norway General The ValkDouble® mounting system must be reinforced by means of tiles, which must be Note 1: The extra ballast must be equally divided over the ballast foundations. placed on the indicated ballast foundations. In three steps you can easily calculate the Note 2: The max.
Page 10
Except Municipalitys: Vindafjord Bremanger near the Ålfotbreen 29 Andøy Hemsedal Eigersund ӕ Moskenes Hemsedal near Sogn og Fj. Sokndal Solund Van der Valk Solar Systems ӕ Røst Selje Bokn Hol near Hordeland / Haugesund Vågsøy røy Klepp Sogn og Fjordane Skjerstad Municipality isn’t in the...
Page 11
Required ballast | Sweden General The ValkDouble® mounting system must be reinforced by means of tiles, which must be Note 1: The extra ballast must be equally divided over the ballast foundations. placed on the indicated ballast foundations. In three steps you can easily calculate the Note 2: The max.
Page 12
Required ballast | Finland General The ValkDouble® mounting system must be reinforced by means of tiles, which must be Note 1: The extra ballast must be equally divided over the ballast foundations. placed on the indicated ballast foundations. In three steps you can easily calculate the Note 2: The max.
Page 13
Required ballast | Poland General The ValkDouble® mounting system must be reinforced by means of tiles, which must be Note 1: The extra ballast must be equally divided over the ballast foundations. placed on the indicated ballast foundations. In three steps you can easily calculate the Note 2: The max.
Page 16
1300 Advised pitch measure 3300 (Based on sun angle of 14,5 ) Panel leng 2128...
Page 17
Valk Hint! 1) Place the mass block on the correct locations before mounting the roof carriers. Detail A 2nd to last hole Front view M8x65 3rd Hole Place the mass block on the rubber tile carriers Mount the mass blocks to the roof carriers in the correct positions. Detail B.1 Detail B.2 15 Nm...
Page 18
Detail A Detail B 15 Nm 3rd hole from end 2nd hole Mount the connector pieces to the roof carriers. Make sure they are placed as shown in the drawing. The groove on the bolt corresponds with the orientation of the bolt head!
Page 19
Detail A Detail B 15 Nm 5th hole from end roof carrier 4th hole Mount the push rods on the roof carriers to connect the two rows. The groove on the bolt corresponds with the orientation of the bolt head!
Page 20
Detail A.1 15 Nm Detail A.2 M8x70 15 Nm Mount in 3rd hole from end of profile 15 Nm Mount in 3rd hole ValkHint!! Create the Aluminium profile with the connector pieces first. Then mount the profile to the roof carrier.
Page 21
Detail A Diagonal rod M8x70 M8x70 15 Nm 15 Nm Mount the push rods to the aluminium profile and the roof carriers.
Page 22
Detail A 15 Nm 4 extra tiles 2 extra tiles Turn upside down 8 extra tiles 6 extra tiles For the required number of tiles check the ballast tables in front of this manual.
Page 23
Step 1 Step 2 Step 3 The the end clamp out of it's slot for an easier assembly. The end clamp can only be turned clockwise, so make sure the end clamp is placed the right way. Step 4 Put the end clamp in the right slot to continue the assembly.
Page 24
Attention!! Do not forget to install the end clamps above the second panel (Same installation as other end clamps, page 07)