5.5.
Climb through the trapdoor, sit on the edge and position the two
lower horizontal braces C on the 2nd rung from the top. Lock the
snap locks firmly in position. (See fig.7)
5.6.
Remaining seated in the same position, put the other two rails C
into position on the top-most rungs. Lock the snap locks firmly into
position. (See fig.8)
5.7.
Install the toe boards. (See fig.9)
5.8.
Lock all wheels prior to using the scaffold.
6. SSCL3 CONTENTS
Reference
B
C
H
F
G
7. SSCL3 ASSEMBLY
NOTE: The mobile scaffold tower may only be assembled, used and dismantled by persons familiar with these Assembly and Use
Instructions.
NOTE: These instructions show the assembly of SSCL1 + SSCL3 from scratch. If you already have SSCL1 assembled it will be
necessary to partly disassemble some of the upper parts so that it resembles diagram No.2 overleaf. The parts removed will be
reused in the assembly of the extended tower.
7.1.
Open folding base A and insert the locking pin in the centre of the folding section. Place diagonal B on one side on the first rung and
on the 4th rung on the other side. Make sure that the butterfly locking part is completely rotated to hold the diagonal firmly in
position. Place horizontal brace C on the first rung and lock in position.
7.2.
Take the two 6 rung end frames, F and 3 diagonals B. Position a diagonal on the topmost rung of one frame and another diagonal on
the second rung of the same frame but on the other side. The last diagonal is to be placed on the top rung of the second end frame.
Make sure that the butterfly locking part is completely rotated to hold the diagonal firmly in position.
WARNING: Make sure that everything is the right way round as per the sketch!).
7.3.
Before climbing within the frame, lock the wheels.
7.4.
Position the end frames on to the folding base and lock the lower diagonal B to the 5th rung of the base frame. Make sure that
the butterfly locking part is completely rotated to hold the diagonal firmly in position. Put the 4 locking pins in place to hold the
frames to the base.
7.5.
Position the 4 stabiliser legs G as per the heights indicated on the sketch. Tighten firmly at the correct angle as shown above.
NOTE: Not all stabiliser legs illustrated.
7.6.
Position platform H on the 5th rung from the bottom.
7.7.
Climb through the trapdoor, sit on the edge and position the two horizontal braces C on the 7th rung from the bottom and the 2
braces C on the 9th rung. Lock the snap locks firmly in position.
7.8.
Stand up on the platform and fix the 2 diagonals B hanging from the frames into position. Make sure that the butterfly locking part is
completely rotated to hold the diagonal firmly in position.
7.9.
Put the two 2-rung guardrail end frames D into position. Slide them onto the frames beneath and secure with locking pins.
7.10.
Place a platform H on the 12th rung from the bottom. Climb through the access hatch, sit on the edge and position the two
horizontal braces C on the 2nd rung from the top.
7.11.
Remaining seated in the same position, put the other two rails C into position on the top-most rungs. Lock the snap locks firmly in
position.
7.12.
Lastly install the toe boards E.
7.13.
Lock all wheels prior to using the scaffold; ensure that the stabiliser legs are secure and firmly seated on the ground.
© Jack Sealey Limited
Description
Quantity
Diagonal Brace
2
Horizontal brace
4
Trapdoor Platform 1
6 Rung End Frame 2