6.2 Powering On the System

Precautions
● Before turning on the AC switch between the SUN2000 and the power grid, use
● If the DC is on and the AC is off, the SUN2000 reports a Grid Failure alarm.
Procedure
Step 1 Turn on the AC switch between the SUN2000 and the power grid.
Step 2 (Optional) Remove the locking screw from the DC switch.
Figure 6-1 Removing the locking screw from a DC switch
Step 3 If there is a DC switch between the PV string and the inverter, turn on the DC
switch.
Step 4 Set the DC SWITCH at the bottom of the SUN2000 to the ON position.
Step 5 Wait for about 1 minute, and then observe the LED indicators of the inverter to
check the running status.
Table 6-2 LED indicator description
Category
Status
Running
LED1
indication
Steady green
Issue 01 (2020-07-02)
NO TICE
a multimeter set to the AC position to check that the AC voltage is within the
specified range.
The SUN2000 starts normally only after the fault is automatically rectified.
LED2
Steady green
Copyright © Huawei Technologies Co., Ltd.
Meaning
N/A
The SUN2000 is operating in grid-
tied mode.
6 Commissioning
57

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents