Huawei NE05E Series Quick Installation Manual page 4

Mid-end, cabinet
Hide thumbs Also See for NE05E Series:
Table of Contents

Advertisement

Precautions
NOTE
This document provides simple and distinctive guidelines for quick hardware installation of the
NE05E&NE08E(NE05E-S2/SE/SF/SG/SH/SI/SQ&NE08E-S6/S6E).
Based on the height of a device, the NE05E-S2/SE/SF/SG/SH/SI/SQ are considered 1 U devices,
and the NE08E-S6/S6E are considered 2 U devices. 1 U = 44.45 mm (1.75 in.)
As the installation methods are similar, the fixed NE05E-SF is used as an example for the 1 U
device, and the card-inserted NE08E-S6 is used as an example for the 2 U device. The installation
differences are specially described in this document.
This document does not describe pre-delivery assembly. This document only describes procedures
for onsite installation.
CAUTION
Electrostatic Discharge
Wear ESD gloves or Antistatic Wrist Strap prior to
contact with the equipment or before handling the
plug-boards, boards, and IC chips to prevent damage
to sensitive components caused by electrostatic
discharge from the human body.
CAUTION
Bundling cables
Binding intervals between cable ties or optical fiber binding straps inside the cabinet cannot
exceed 250 mm.
CAUTION
Pre-Installation Check
Verify that the equipment room, power supply, ground cables and optical cables are ready for
installation. Start the installation according to the engineering design documents after confirming
that conditions are met. Refer to the Installation Guide for information about specific operational
requirements and technical specifications.
1

Advertisement

Table of Contents
loading