Procedure
Step 1 Check cable connections and the mechanical performance.
1.
2.
Step 2 Check the insulation only after the upstream and downstream circuit breakers in the PDC are
switched off.
1.
Issue 01 (2017-07-15)
4
The power-on commissioning process requires at least two qualified electricians, one
responsible for operations and the other for monitoring.
Cautions and warnings must be properly placed onsite.
Users are categorized as admin and operator. Admin users have more rights than operator
users.
Powering off the PDC disconnects the power supply to the downstream devices. Exercise
caution with this operation when the PDC is supplying power to a working system.
Check that cables are connected correctly outside the cabinet. Check that all bolts are
secured for inlet and outlet cables and tighten a bolt if it is loose.
Check that ground cables are properly connected.
Switch off the upstream circuit breaker QFS for the SPD in the input module of the PDC,
and switch on other circuit breakers.
Figure 4-1 Switching off the SPD circuit breaker
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.

Power-On Commissioning

4 Power-On Commissioning
18

Advertisement

Table of Contents
loading

This manual is also suitable for:

Pdu8000 series

Table of Contents