Figure 31. Connecting Ground Cable (1) - Samsung 310 5G CPE Installation Manual

Outdoor unit
Hide thumbs Also See for 310 5G CPE:
Table of Contents

Advertisement

Category
Description
Fastener
MGB
CPE
Outdoor
Recommended
M6 SEMS
Torque Value
• Cable Cutter
Working Tools
• Wire Stripper
• Crimping tool
• Heating Gun
• Nipper
• Screw Driver ('+', Number 3)
• Torque Driver (20-90 lbf·in.)
• Screw Driver Bit ('+', Number 3)
For the pressure terminals of the cable, the UL Listed products or equivalent must
be used.
Example: Manufacturer-Panduit
CPE Outdoor: 14 AWG Pressure Terminal (LCD10-14A-L)
2

Figure 31. Connecting Ground Cable (1)

MGB
3
4
5
5G CPE Outdoor Installation Manual v1.0
Copyright © 2018, All Rights Reserved.
Checking MGB specifications per site and preparing connecting parts
M6 × L12 SEMS (Hexagon+)/2 EA
43 lbf·in (50 kgf·cm)
Install the ground cable from the MGB to the CPE Outdoor ground terminal as
shown in the figure below.
Ground Cable
Assemble a pressure terminal and a heat shrink tube at the end of the CPE
Outdoor ground cable.
Align the pressure terminal to the mounting hole of the CPE Outdoor ground
terminal.
Firmly fix the pressure terminal onto the CPE Outdoor ground terminal using
fasteners.
Confidential
Chapter 3 Connecting Cables
[Rear View]
37