10.Select time of day mode in the "Options" tab of the CP16x3 properties dialog.
11.Configure SERVER1B in the same way as SERVER1A.
12.Transfer the PC station configurations from the SIMATIC Manager to both the OS servers
via the "PLC > Configure ..." command (See also Engineering Station (Page 56)).
13.Load the configuration via the "PLC > Download..." command in the program.
The following figure illustrates the configuration of the plant bus, whereby all tasks are
performed from the central ES.
Compendium Part A - Configuration Guidelines (V8.2)
Configuration Manual, 08/2016, A5E38166869-AA
Creating and managing a PCS 7 project
5.5 Adding Additional Stations
67