3. The dialog below shows how the download procedure is progressing; this procedure must
be completed successfully.
4. You can call the load log for the server as well as for the client once the download procedure
is complete. All the actions performed during the download procedure are recorded in this
log, together with the time and date when they were executed.
In the component view, select the OS, followed by the "Display load log..." menu command.
Compendium Part A - Configuration Guidelines (V8.2)
Configuration Manual, 08/2016, A5E38166869-AA
Configuring OS functions
10.10 Downloading the OS projects
285