5. Operating Procedures
5-1 Startup Procedures (Single Unit)
Before starting up the UPS system, be sure to check the following items first.
Ensure all circuit breakers are cut off and switched to OFF, as well as the breaker
or fuse of the external battery cabinet.
Confirm if the locking latch is located at "".
Confirm if there is no voltage potential between NEUTRAL and Ground.
Confirm if the input power source matches the rated voltage, frequency, phase
and battery of the UPS that you have installed.
Q4
Q3
Q2
Q1
Q1: Input Circuit Breaker
Q2: Bypass Input Circuit Breaker
Q3: Manual Bypass Switch
Q4: Output Circuit Breaker
5-1
Off
Fail On