Mount The Clamp; Install The Cable Management System; Prepare For Commissioning - ABB InCharge Terra 184 Manual

All-in-one 90kw dc fast charger
Hide thumbs Also See for InCharge Terra 184:
Table of Contents

Advertisement

Installation
5.8.2

Mount the clamp

For the specifications for the cable management system, refer to section 10.11.
1. Pull the wire and hold it firmly. At the same time connect the clamp to the wire.
Apply a knot.
The correct location for mounting the clamp is at approximately half way on the
EV charge cable.
2. Slowly release the wire.
The EV charge cable folds with one loop, depending on the cable length.
5.8.3

Install the cable management system

1. Install the head (A) on the EVSE in the
eyebolt hole.
2. Tighten the fasteners (B) first on the
top part, then in the lower part.
5.9

Prepare for commissioning

Preliminary requirements
56
Installation engineer
Danger:
Hazardous voltage
Do not commission the EVSE. Only a service engineer of the
manufacturer is qualified to commission the EVSE.
A
B
B
9AKK108466A3703-EN | 001

Advertisement

Table of Contents
loading