12 Installing the Electronic Door Lock System

12.3 Post-installation Check

No.
1
Boards support easy removal and reinstallation.
2
The ELU port is connected correctly.
3
The door locks are correctly installed, and cables are
correctly connected.
4
Monitoring cables and AC power cables are not bundled
together, and the cables are neatly and securely routed.
5
All power cables must use jointless copper cores and
correctly connected according to operation standards.
6
All cables are intact without joints between two ends.
7
The cabinet interior is clean without foreign materials, and
the air intake/exhaust vent is not blocked.
To Verify That...
Check by trial use.
Check the port connection.
Check the door locks and their connections.
Check cable routing.
Check all power cables and power cable
connections.
Check all cables.
Check the interior of the cabinet and air vents.