3-7-18.
S1
Post
Replacement and Adjustment
(Removal of S1 Post Loading Arm Unit)
1.
Remove the top panel.
2.
Remove the front loading unit.
3.
Remove the S5 Post Base Unit. (Refer to S5 Post
Base Unit Replacement.)
4.
Remove the tension arm unit. (Refer to Tension Arm
Unit Replacement.)
5.
Remove the screw (A) and remove the S1 Post from
the loading rail.
6.
Remove the E ring (A) and remove the S1 Loading
Arm Unit.
Hole (B)
E Ring (A)
T1 Loading Arm Unit
Loading
Arm
Unit
Hole (A)
S1 Loading Arm Unit
S1 Loading Arm Unit
S1 Post Loading Arm Unit Removal
(Installation of S1 Post Loading Arm Unit)
1.
Install a new S1 Post Loading Arm Unit as reverse
order of removal. After its installation S1 Post
Loading Arm Unit Phase Adjustment is necessary.
2.
After its installation confirm the S1 Post moves
smoothly on the loading rail. Then Adjust the
Tension Arm and Linearity.
(Adjustment Procedure)
1.
When S1 Post Loading Arm is installed, the hole (A)
and (B) must be parallel.
Loading Arm Unit
Screw (E)
Screw (D)
Screw (A)
Screw (C)
T1 Post Unit