Section 9
Establishing connection and verifying the IEEE C37.118/1344 communication
9.6
78
IEC140000145 V1 EN
Figure 18:
Verifying the UDP communication using PMU Connection Tester
•
Now it should be possible to see the streaming synchrophasor data.
•
Verify the communication by following the same steps as in section
IEEE C37.118/1344 TCP
Optical budget calculation for RES670 - PDC
communication
Most of the times, the RES670 IEDs are located in the substations. A local PDC might be
located in the substation. For communications within the substation or between the
RES670 and the WAN/LAN access point, it is important to know what is the optical
budget available. The graph in Figure
– PDC configuration using typical OEMs.
communication.
19
shows the dynamic range available for a PMU
1MRK 511 366-UUS -
IEC140000145-1-en.vsd
Verifying the
Commissioning manual