1900/27 Vibration Monitor Operation and Maintenance Manual
To install the cable to the terminal strip follow these steps:
1. If an outer jacket is on the relay cable then strip off about 25 mm (1
2. Strip 6 mm (0.25 in) of insulation from each of the conductors that
3. Crimp a ring or spade lug to each of the conductors using the crimp
4. Open the hinged protective cover over the power and relay terminal
5. Place each lug under the proper screw on the relay terminal strip
6. Close the hinged protective cover over the terminal strip.
18
in) of outer insulation from the cable.
will be used by the relay.
tool.
strip.
(see Figure 2-12) and use the screwdriver to tighten the screw.
Figure 2-12: Alert and Danger Relay Connections