SECTION 5-Programmer Installation

5.1-General lnformation
The programmer is attached to the bracket mounted to
the left side of the breaker's center channel as shown in
Fig. 2-9. The guide pins on this bracket mate with the holes on
either side of the programmer connector. The guide pins pro­
vide the necessary alignment for the connector engagement.
The locking lever engages with the pin which is assembled to
the programmer frame and secures the programmer to the
mounting bracket.

5.2-AK/AKS-50 Installation

The AKS-50 mounting bracket is shown in Fig. 5-1. Instal­
lation is as follows:
1. Insert the guide pins into the hole and push on the
programmer. This will engage the connectors and release
the locking lever which will move upwards.
2. Verify that the locking lever actually engaged the
programmer pin.
To remove the programmer:
releasing the programmer pin.
5.3-AK/AKR-75/1 00 Installation
The AK/AKR-75/100 mounting bracket is shown in Fig. 2-9.
Installation is as follows:
programmer, engagi � g the connectors.
grammer.
programmer pin.
To remove the programmer pull out the locking lever which
will release the programmer pin. Remove the programmer.
Fig. 5-1. AKS-50 programmer mounting
1. Move locking lever to horizontal position, thus
2. Remove programmer.
1. Insert the guide pins into the holes and push on the
2. The locking lever is released, securing the pro­
Verify that the locking lever actually engaged the
3.