Figure 4-20 Wizard Startup
Step 2 Tap Yes to enter the screen for checking before startup.
Figure 4-21 Checking before startup
Step 3 Tap Yes to check items one by one as prompted.
Step 4 Tap Yes to enter the screen for selecting commissioning items.
Step 5 Tap Yes. The screen for component commissioning is displayed.
Step 6 View the commissioning result.
Issue 02 (2022-03-30)
NO TE
● For the initial wizard startup, Last Record is in gray, indicating that operation is not
allowed.
● For a non-initial wizard startup, you can choose Last Record to view the last wizard
startup report.
NO TE
All the items are selected by default if you enter the screen for selecting commissioning
items for the first time. You can deselect any commissioning items except "Indoor fan
commissioning."
NO TE
The fan commissioning item is mandatory. After commissioning for a component succeeds,
the system automatically performs commissioning for the next component you selected. If
commissioning fails, wizard startup ends.
Copyright © Huawei Technologies Co., Ltd.
4 Power-On Commissioning
98

Advertisement

Table of Contents
loading

This manual is also suitable for:

Netcol8000-c190d40edNetcol8000-c190d40ec

Table of Contents