29 COMMISSIONING AND TESTING
A. Electrical Installation
1. Checks to ensure electrical safety should be carried out by a
competent person.
2. ALWAYS carry out the preliminary electrical system checks,
i.e. earth continuity, polarity, resistance to earth and short
circuit, using a suitable test meter.
3. After wiring the boiler, all grommets in the bottom panel
MUST be in place to ensure that the boiler case sealing is
maintained.
WARNING.
Whilst effecting the required gas tightness test and purging air from the gas installation,
open all windows and doors, extinguish naked lights and DO NOT SMOKE.
GENERAL
Please Note: The combustion for this appliance has
been checked, adjusted and preset at the factory for
operation on the gas type defined on the appliance
data plate. DO NOT adjust the air/gas ratio valve.
Having checked:
-
That the boiler has been installed in accordance
with these instructions.
-
The integrity of the flue system and the flue seals,
as described in the Flue Installation section.
Proceed to put the boiler into operation as follows:
CHECK THE OPERATIONAL (WORKING) GAS
INLET PRESSURE
Set up the boiler to operate at maximum rate.
With the boiler operating in the maximum rate
condition check that the
operational (working) gas
pressure at the inlet gas pressure
test point complies with the
requirements - refer to "Gas
Supply" on page 10.
Ensure that this inlet pressure
can be obtained with all other
gas appliances in the property
working.
205552-10118
As part of the commissioning process, the combustion of this appliance must be checked
and the Benchmark Checklist completed. A flow chart to assist is provided on page 61.
IT IS A CONDITION OF THE MANUFACTURERS WARRANTY THAT THE
BENCHMARK COMMISSIONING CHECKLIST IS FULLY COMPLETED
32
INSTALLATION
B. Gas Installation
1. The whole of the gas installation, including the meter,
2. Purge air from the gas installation by the approved methods
Gas
Supply
Gas Pressure
Test Point
ATTENTION !
AND LEFT WITH THE APPLIANCE
should be inspected and tested for tightness and purged in
accordance with the recommendations of BS. 6891.
In IE refer to IS.813:2002.